County System Project List - As Planned for the Bid Opening shown
County |
Bid Opening |
Job Piece |
Project |
Hwy. No |
Work Type Description |
Job Description |
Length |
Estimated Cost |
Fund Code |
ARRA Funds |
Federal Funds |
State Funds |
Other Funds |
|
ADAIR |
04/2009 |
1958004 |
BRO -STIM (188) CO |
COBRGE |
BRIDGE & APPROACHES |
CO RD(PEAVINE ROAD) 4 MILE NORTH & 0.2 MILE EAST OF NORTH JUNCTION US-59/SH-51(REPL. LOW WATER XING) |
0.25 |
$636,637.00 |
0C250 |
$515,676.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$120,961.00 |
Project Total |
$636,637.00 |
|
$515,676.00 |
$0.00 |
$0.00 |
$120,961.00 |
|
ALFALFA |
04/2009 |
1894904 |
STP -STIM (224) CO |
CO RD |
RESURFACE |
CO RD: ON NS-271, FROM SH-45, 1.0 MILE WEST OF GOLTRY, NORTH |
2.2 |
$1,100,113.00 |
0C200 |
$605,062.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 0L250 |
$0.00 |
$396,041.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$99,010.00 |
Project Total |
$1,100,113.00 |
|
$605,062.00 |
$396,041.00 |
$0.00 |
$99,010.00 |
|
BEAVER |
05/2009 |
2204104 |
BRO -STIM (225) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR: (NS-146) OVER COON CR, APPROX. 7.0 MI EAST & 3.5 MI SOUTHOF ELMWOOD |
0.2 |
$556,274.00 |
0C200 |
$556,274.00 |
$0.00 |
$0.00 |
$0.00 |
|
BEAVER |
05/2009 |
2366304 |
BRF -STIM (232) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR. OVER BULL CR., 3.0 MI WEST & 3.4 MI NORTH OF THE SH-3/US-83JCT AT BRYAN'S CORNER (NS-119) |
0.1 |
$556,274.00 |
09012 |
$0.00 |
$0.00 |
$0.00 |
$27,814.00 |
|
|
|
|
|
|
|
|
| 0C200 |
$433,893.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 0L1C0 |
$0.00 |
$94,567.00 |
$0.00 |
$0.00 |
Project Total |
$556,274.00 |
|
$433,893.00 |
$94,567.00 |
$0.00 |
$27,814.00 |
|
BECKHAM |
05/2009 |
2306004 |
BRO -STIM (219) RB |
COBRGE |
BRIDGE & APPROACHES |
CO. BR. OVER BUFFALO CREEK LOCATED 7.5 MILES NORTH OF ERICK ON EW-117 |
0 |
$721,361.00 |
0CIRB |
$0.00 |
$0.00 |
$0.00 |
$93,777.00 |
|
|
|
|
|
|
|
|
| 0C200 |
$627,584.00 |
$0.00 |
$0.00 |
$0.00 |
Project Total |
$721,361.00 |
|
$627,584.00 |
$0.00 |
$0.00 |
$93,777.00 |
|
BRYAN |
05/2009 |
1967304 |
BRF -STIM (195) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR: OVER ISLAND BAYOU & TRIBUTARY, APPROX 2.6 MILES NORTH OFSH-78 ON NS 380 |
0.4 |
$647,990.00 |
0C250 |
$647,990.00 |
$0.00 |
$0.00 |
$0.00 |
|
BRYAN |
05/2009 |
2165504 |
BRO -STIM (196) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR OVER RED BRANCH CR APPROX.1.0 MI NORTH & 1.5 MI EASTOF SMITH-LEE |
0.3 |
$421,919.00 |
0C250 |
$421,919.00 |
$0.00 |
$0.00 |
$0.00 |
|
CANADIAN |
04/2009 |
2156304 |
BRO -STIM (212) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR: OVER AN UNNAMED CREEK, 1.0 MI SOUTH & 3.9 MI WESTOF PIEDMONT |
0.2 |
$734,876.00 |
0L110 |
$0.00 |
$213,114.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 0C200 |
$462,972.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$58,790.00 |
Project Total |
$734,876.00 |
|
$462,972.00 |
$213,114.00 |
$0.00 |
$58,790.00 |
|
CANADIAN |
04/2009 |
2156704 |
BRO -STIM (213) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR: OVER A TRIB OF THE N. CANADIAN RIVER, 2.0 MI NORTH &3.6 MI EAST OF GEARY |
0.2 |
$328,376.00 |
0C200 |
$206,877.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$26,270.00 |
|
|
|
|
|
|
|
|
| 0L110 |
$0.00 |
$95,229.00 |
$0.00 |
$0.00 |
Project Total |
$328,376.00 |
|
$206,877.00 |
$95,229.00 |
$0.00 |
$26,270.00 |
|
CHEROKEE |
05/2009 |
2343104 |
BRF -STIM (189) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR. OVER TELAMAY HOLLOW CREEK, 3.2 MI EAST & 0.5 MI NORTH OF MOODY |
0.23 |
$479,723.00 |
0C250 |
$388,576.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$91,147.00 |
Project Total |
$479,723.00 |
|
$388,576.00 |
$0.00 |
$0.00 |
$91,147.00 |
|
CIMARRON |
05/2009 |
2343904 |
BHF -STIM (226) CO |
COBRGE |
BRIDGE REHABILITATION |
CO. BR. OVER THE BEAVER RIVER, 1.2 MI NORTH OF FELT, ON NS-13 |
0 |
$248,528.00 |
0C200 |
$248,528.00 |
$0.00 |
$0.00 |
$0.00 |
|
COAL |
04/2009 |
2300204 |
BRO -STIM (200) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR.: OVER COAL CR. 2.5 MI. EAST & 2.2 MI. SOUTH OF LEHIGH,ON NS-384 |
0.2 |
$509,307.00 |
0L110 |
$0.00 |
$157,885.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 0C250 |
$295,398.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$56,024.00 |
Project Total |
$509,307.00 |
|
$295,398.00 |
$157,885.00 |
$0.00 |
$56,024.00 |
|
COAL |
04/2009 |
2357604 |
BRO -STIM (201) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR: OVER TRIB. TO KEEL CREEK, 7.8 MI NORTH & 7.2 MI EAST OF COALGATE |
0.2 |
$395,268.00 |
0L110 |
$0.00 |
$86,959.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$146,249.00 |
|
|
|
|
|
|
|
|
| 0C250 |
$162,060.00 |
$0.00 |
$0.00 |
$0.00 |
Project Total |
$395,268.00 |
|
$162,060.00 |
$86,959.00 |
$0.00 |
$146,249.00 |
|
COTTON |
04/2009 |
2219504 |
BRO -STIM (214) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR.: ON (EW-185) OVER A TRIB. TO EASR CACHE CR., 2.0 MI SOUTH &1.0 MI EAST OF SH-53/SH-5 JCT., IN WALTERS |
0.25 |
$380,039.00 |
0L110 |
$0.00 |
$110,211.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 0C200 |
$239,425.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$30,403.00 |
Project Total |
$380,039.00 |
|
$239,425.00 |
$110,211.00 |
$0.00 |
$30,403.00 |
|
CUSTER |
05/2009 |
2235904 |
BRO -STIM (220) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR.: OVER BARNITZ CR., 4.0 MI WEST & 3.5 MI NORTH OF CLINTON |
0.2 |
$509,717.00 |
0C200 |
$509,717.00 |
$0.00 |
$0.00 |
$0.00 |
|
DEWEY |
04/2009 |
2134304 |
BRF -STIM (221) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR: OVER THE SOUTH CANADIAN RIVER, 1.7 MILES NORTH AND6.8 MILES WEST OF OAKWOOD |
0.379 |
$1,782,141.00 |
0C200 |
$1,782,141.00 |
$0.00 |
$0.00 |
$0.00 |
|
GARFIELD |
04/2009 |
2254504 |
BRO -STIM (227) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR.: OVER SKELETON CR., 0.6 MI NORTH & 6.6 MI EAST OFWAUKOMIS (CN #188) |
0.25 |
$689,292.00 |
0C200 |
$689,292.00 |
$0.00 |
$0.00 |
$0.00 |
|
GARVIN |
04/2009 |
2261404 |
BRF -STIM (208) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR. OVER UNNAMED CREEK, 3.5 MILES NORTH OF SH-7. |
0.3 |
$680,332.00 |
0C200 |
$544,266.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$27,213.00 |
|
|
|
|
|
|
|
|
| 0L1C0 |
$0.00 |
$108,853.00 |
$0.00 |
$0.00 |
Project Total |
$680,332.00 |
|
$544,266.00 |
$108,853.00 |
$0.00 |
$27,213.00 |
|
GRANT |
04/2009 |
2265704 |
BRO -STIM (228) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR. OVER SAND CREEK, I MILE NORTH AND 1.5 MILES EAST OF THESH-11/SH-132 JCT |
0.25 |
$524,019.00 |
0C200 |
$524,019.00 |
$0.00 |
$0.00 |
$0.00 |
|
GRANT |
04/2009 |
2555304 |
STP -STIM (229) CO |
CO RD |
RESURFACE |
CO. RD. BEGIN 5.3 MI. S. OF POND CREEK @ GARFIELD C/L, EXTEND N. 5.3 MI. |
5.3 |
$1,365,635.00 |
0C200 |
$109,251.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$259,471.00 |
|
|
|
|
|
|
|
|
| 0L250 |
$0.00 |
$996,913.00 |
$0.00 |
$0.00 |
Project Total |
$1,365,635.00 |
|
$109,251.00 |
$996,913.00 |
$0.00 |
$259,471.00 |
|
GREER |
04/2009 |
2306404 |
BRO -STIM (222) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR. OVER UNNAMED CR, 5.5 MI WEST & 3.0 MI SOUTH OF WILLOWON NS-189 |
0 |
$326,469.00 |
0C200 |
$326,469.00 |
$0.00 |
$0.00 |
$0.00 |
|
HUGHES |
06/2009 |
2255404 |
BRF -STIM (202) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR.: OVER BIG CR., 0.3 MI NORTH & 3.6 MI EAST OF ALLEN(LOCAL # 38A) |
0.3 |
$783,613.00 |
0C250 |
$430,987.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$125,378.00 |
|
|
|
|
|
|
|
|
| 0L1C0 |
$0.00 |
$227,248.00 |
$0.00 |
$0.00 |
Project Total |
$783,613.00 |
|
$430,987.00 |
$227,248.00 |
$0.00 |
$125,378.00 |
|
JEFFERSON |
04/2009 |
2265804 |
BRO -STIM (215) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR. OVER MUD CREEK, 7.8 MILES WEST SH-89 ON EW-193 |
0.25 |
$757,181.00 |
09012 |
$0.00 |
$0.00 |
$0.00 |
$60,574.00 |
|
|
|
|
|
|
|
|
| 0L110 |
$0.00 |
$219,583.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 0C200 |
$477,024.00 |
$0.00 |
$0.00 |
$0.00 |
Project Total |
$757,181.00 |
|
$477,024.00 |
$219,583.00 |
$0.00 |
$60,574.00 |
|
KINGFISHER |
04/2009 |
2141504 |
BRF -STIM (230) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR: OVER A TRIBUTARY OF CAMPBELL CREEK, 4.5 MILES WEST OF SH-74F INCASHION |
0.2 |
$647,528.00 |
0C200 |
$647,528.00 |
$0.00 |
$0.00 |
$0.00 |
|
LATIMER |
05/2009 |
2347404 |
BRO -STIM (197) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR. OVER PEACHLAND CR, APPROX. 0.7 MI NORTH 2.0 MI WEST OFBENGAL |
0.2 |
$615,580.00 |
0C250 |
$615,580.00 |
$0.00 |
$0.00 |
$0.00 |
|
LEFLORE |
04/2009 |
2034804 |
BRO -STIM (198) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR: OVER FOURCHE MALINE CREEK, 1.5 MI NORTH & 2.3 MI EAST OF LEFLORE |
0.5 |
$1,101,743.00 |
0C250 |
$925,464.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$176,279.00 |
Project Total |
$1,101,743.00 |
|
$925,464.00 |
$0.00 |
$0.00 |
$176,279.00 |
|
LINCOLN |
04/2009 |
2202704 |
BRO -STIM (203) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR: OVER SPRING CREEK, 1.0 MI WEST & 0.7 MI SOUTH OFUS-177/SH-66 JCT. |
0.3 |
$439,271.00 |
0L110 |
$0.00 |
$140,567.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 0C250 |
$259,170.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$39,534.00 |
Project Total |
$439,271.00 |
|
$259,170.00 |
$140,567.00 |
$0.00 |
$39,534.00 |
|
LOGAN |
04/2009 |
2289104 |
BRO -STIM (209) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR.: ON EW-81, OVER BLUE CR., 4.2 MI WEST OF MERIDIAN |
0.21 |
$567,226.00 |
0C200 |
$567,226.00 |
$0.00 |
$0.00 |
$0.00 |
|
LOVE |
04/2009 |
2392304 |
BRO -STIM (216) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR. OVER SIMON CR. 5.3 MI NORTH & 3.0 MI EAST OF SH-76/SH-32 JCT.(REPLACE LOW WATER CROSSING) |
0.12 |
$761,715.00 |
0C200 |
$479,881.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 0L110 |
$0.00 |
$220,897.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$60,937.00 |
Project Total |
$761,715.00 |
|
$479,881.00 |
$220,897.00 |
$0.00 |
$60,937.00 |
|
MCINTOSH |
04/2009 |
2222404 |
BRO -STIM (190) CO |
COBRGE |
BRIDGE & APPROACHES |
CO.BR. OVER FLAT ROCK CREEK, 0.1 MILE NORTH OF RAIFORD |
0.25 |
$410,018.00 |
09012 |
$0.00 |
$0.00 |
$0.00 |
$77,903.00 |
|
|
|
|
|
|
|
|
| 0C250 |
$332,115.00 |
$0.00 |
$0.00 |
$0.00 |
Project Total |
$410,018.00 |
|
$332,115.00 |
$0.00 |
$0.00 |
$77,903.00 |
|
MAYES |
04/2009 |
2164404 |
BRO -STIM (183) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR: OVER CHOUTEAU CR, APPROX 0.3 MI SOUTH & 2.3 MI EAST OF CHOUTEAU |
0.06 |
$1,258,008.00 |
0C250 |
$1,258,008.00 |
$0.00 |
$0.00 |
$0.00 |
|
MAYES |
06/2009 |
2275404 |
BRO -STIM (184) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR.: OVER BRUSHY CR. APPROX 2.2 MI S & 2.5 MI WEST OF THE US-412/US-69 JCT |
0.02 |
$301,571.00 |
0C250 |
$301,571.00 |
$0.00 |
$0.00 |
$0.00 |
|
MURRAY |
04/2009 |
2266804 |
BRO -STIM (210) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR. OVER GUY SANDY CREEK, 7.6 MILES NORTH AND .7 MILE WEST OFSULPHUR IN MURRAY COUNTY |
0.25 |
$791,992.00 |
0C200 |
$791,992.00 |
$0.00 |
$0.00 |
$0.00 |
|
MUSKOGEE |
05/2009 |
1844904 |
BRO -STIM (191) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR. OVER CLOUD CR., 1.3 MI NORTH & 1.6 MI EAST OF BOYTON |
0.365 |
$718,769.00 |
0C250 |
$438,449.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 0L110 |
$0.00 |
$143,754.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$136,566.00 |
Project Total |
$718,769.00 |
|
$438,449.00 |
$143,754.00 |
$0.00 |
$136,566.00 |
|
NOBLE |
04/2009 |
2142404 |
BRO -STIM (231) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR: OVER RED ROCK CREEK, 0.7 MI WEST OF THE US-77/SH-15 JCT SOUTHWEST OF CERES |
0.2 |
$919,151.00 |
0C200 |
$919,151.00 |
$0.00 |
$0.00 |
$0.00 |
|
OKFUSKEE |
04/2009 |
2164304 |
BRO -STIM (204) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR: OVER HARRICAN CREEK, 0.4 MILES WEST AND 3.0 MILESSOUTH OF MICAWBER |
0.24 |
$704,179.00 |
0L110 |
$0.00 |
$211,254.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 0C250 |
$401,382.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$91,543.00 |
Project Total |
$704,179.00 |
|
$401,382.00 |
$211,254.00 |
$0.00 |
$91,543.00 |
|
OKMULGEE |
04/2009 |
2218004 |
BRO -STIM (192) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR.: OVER UNNAMED CR., 4.2 MI EAST & 2.0 MI NORTH OFUS-75/SH-16 JCT. |
0.2 |
$390,958.00 |
0C250 |
$316,676.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$74,282.00 |
Project Total |
$390,958.00 |
|
$316,676.00 |
$0.00 |
$0.00 |
$74,282.00 |
|
PAYNE |
04/2009 |
2217004 |
BRO -STIM (211) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR.: OVER CLEAR CR, 1.9 MI EAST & 7.0 MI SOUTH OF THE I-35/SH-51 JCT. |
0.25 |
$465,736.00 |
0C200 |
$465,736.00 |
$0.00 |
$0.00 |
$0.00 |
|
PITTSBURG |
04/2009 |
2141604 |
BRF -STIM (199) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR OVER UNNAMED CREEK APPROX. 2.0 MI NORTH & 3.7 MI WESTWEST OF QUINTON |
0.3 |
$328,075.00 |
0C250 |
$328,075.00 |
$0.00 |
$0.00 |
$0.00 |
|
PITTSBURG |
08/2009 |
2348205 |
STP -STIM (233) CI |
COBRGE |
GRADE, DRAIN & SURFACE |
CO. BR. OVER LAKE EUFAULA APPROX. 2 MI EAST OF CROWDER, EAST 0.75 MI(PHASE I) (ROADWAY) (6110C) |
0.1 |
$3,800,000.00 |
0C200 |
$450,000.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 0CIRB |
$0.00 |
$0.00 |
$0.00 |
$2,350,000.00 |
|
|
|
|
|
|
|
|
| 00BIA |
$0.00 |
$0.00 |
$0.00 |
$1,000,000.00 |
Project Total |
$3,800,000.00 |
|
$450,000.00 |
$0.00 |
$0.00 |
$3,350,000.00 |
|
PONTOTOC |
06/2009 |
2277604 |
BRO -STIM (205) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR.: OVER GRAYSON CR., 2.0 MI SOUTH & 6.7 MI EAST OFSH-59A /SH-3W JCT |
0.02 |
$706,593.00 |
0C250 |
$388,626.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$105,989.00 |
|
|
|
|
|
|
|
|
| 0L110 |
$0.00 |
$211,978.00 |
$0.00 |
$0.00 |
Project Total |
$706,593.00 |
|
$388,626.00 |
$211,978.00 |
$0.00 |
$105,989.00 |
|
PONTOTOC |
06/2009 |
2277704 |
BRO -STIM (206) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR.: OVER MILL CREEK, 0.5 MI NORTH & 2.0 MI EAST OF FITTSTOWN |
0.02 |
$673,527.00 |
0L110 |
$0.00 |
$148,176.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 0C250 |
$276,146.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$249,205.00 |
Project Total |
$673,527.00 |
|
$276,146.00 |
$148,176.00 |
$0.00 |
$249,205.00 |
|
POTTAWATOMIE |
06/2009 |
2307504 |
BRF -STIM (207) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR.: OVER POPSHEGO CR, 0.5 MI NORTH & 2.9 MI EAST OFST. LOUIS |
0.02 |
$914,208.00 |
0C250 |
$493,673.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$155,415.00 |
|
|
|
|
|
|
|
|
| 0L1C0 |
$0.00 |
$265,120.00 |
$0.00 |
$0.00 |
Project Total |
$914,208.00 |
|
$493,673.00 |
$265,120.00 |
$0.00 |
$155,415.00 |
|
SEQUOYAH |
05/2009 |
2003204 |
BRO -STIM (193) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR(NS-467) OVER PRAIRIE CREEK APPROX 1.6 MILE SOUTH & 1.0 MILE WEST OFAKINS. (REPLACE EXIST LOW WATER XING) |
0.25 |
$519,606.00 |
0C250 |
$420,881.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$98,725.00 |
Project Total |
$519,606.00 |
|
$420,881.00 |
$0.00 |
$0.00 |
$98,725.00 |
|
STEPHENS |
04/2009 |
2420304 |
BRF -STIM (217) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR OVER DEER CR, 3.5 MI SOUTH & 7.7 MI EAST OF SH-53/US-81 JCT |
0 |
$607,866.00 |
0L1C0 |
$0.00 |
$176,281.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 0C200 |
$382,956.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$48,629.00 |
Project Total |
$607,866.00 |
|
$382,956.00 |
$176,281.00 |
$0.00 |
$48,629.00 |
|
STEPHENS |
04/2009 |
2420404 |
BRF -STIM (218) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR OVER STAGE STAND CR, 6.0 MI SOUTH & 6.0 MI WEST OF THE NORTHSH-7/US-81 JCT, |
0 |
$707,603.00 |
0L1C0 |
$0.00 |
$205,205.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 0C200 |
$445,790.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$56,608.00 |
Project Total |
$707,603.00 |
|
$445,790.00 |
$205,205.00 |
$0.00 |
$56,608.00 |
|
TILLMAN |
04/2009 |
2378204 |
BRO -STIM (223) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR. OVER DEEP RED CR., 0.6 MI. S. & 3.2 MI. E. OF LOVELAND, OKLAHOMA ONNS-239 |
0.2 |
$471,017.00 |
0C200 |
$471,017.00 |
$0.00 |
$0.00 |
$0.00 |
|
TULSA |
05/2009 |
2503104 |
BRO -STIM (185) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR. OVER DELAWARE CR. OVERFLOW ON CINCINNATI AVE. 0.5 MI. SOUTHOF 86TH ST. NORTH |
0.4 |
$1,199,867.00 |
0C250 |
$935,896.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$263,971.00 |
Project Total |
$1,199,867.00 |
|
$935,896.00 |
$0.00 |
$0.00 |
$263,971.00 |
|
WAGONER |
04/2009 |
2125804 |
BRO -STIM (194) CO |
COBRGE |
BRIDGE & APPROACHES |
CO BR: 1.0 MI NORTH & 4.25 MI WEST OF US-69/SH-51 IN WAGONER |
0.125 |
$364,194.00 |
0C250 |
$294,997.00 |
$0.00 |
$0.00 |
$0.00 |
|
|
|
|
|
|
|
|
| 09012 |
$0.00 |
$0.00 |
$0.00 |
$69,197.00 |
Project Total |
$364,194.00 |
|
$294,997.00 |
$0.00 |
$0.00 |
$69,197.00 |
|
WASHINGTON |
05/2009 |
2221104 |
STP -STIM (186) CO |
COBRGE |
BRIDGE & APPROACHES |
CO.BR. OVER UNNAMED CREEK ON N401, 0.6MI SOUTH AND 4.2MI EAST OF JCT US-75AND OK-KS BORDER. REPLACE LOW WATER CROSSING |
0.02 |
$699,441.00 |
0C250 |
$699,441.00 |
$0.00 |
$0.00 |
$0.00 |
|
WASHINGTON |
05/2009 |
2355004 |
BRO -STIM (187) CO |
COBRGE |
BRIDGE & APPROACHES |
CO. BR. OVER BRUSH CREEK APPROX. 0.8 MI. SOUTH AND 2.0 MI. EAST OF US-75/SH-10 EAST JCT. (REPLACE LOW WATER CROSSING) |
0.2 |
$524,570.00 |
0C250 |
$524,570.00 |
$0.00 |
$0.00 |
$0.00 |
|
Information source is the ODOT Programs Division Job Piece system - Sat 3/21/2009 3:55:07 PM
Note: This potential project list has been compiled in support of ARRA project preparations.
All data should be considered preliminary and will be subject to change without notice. The completion of the
encompassed projects on an accelerated schedule is entirely dependent upon the subsequent availability of
ARRA funding. The projects may be ultimately financed with multiple funding sources.
|