Note: This potential project list has been compiled in support of ARRA project preparations. All data should be considered preliminary and will be subject to change without notice. The completion of the encompassed projects on an accelerated schedule is entirely dependent upon the subsequent availability of ARRA funding. The projects may be ultimately financed with multiple funding sources.




County Bid
Opening
Job
Piece
Project Hwy.
No
Work Type
Description
Job
Description
Length Estimated
Cost
Fund
Code
ARRA
Funds
Federal
Funds
State
Funds
Other
Funds

CANADIAN / 2674104 STP -STIM (403) AG CT ST RESURFACE MUSTANG ARRA: N SARA RD FROM SH-152 TO SW 59TH & S MUSTANG RDFROM SW 89TH TO SH-152 2 $568,920.00 0C230 $517,200.00 $0.00 $0.00 $0.00
0L230 $0.00 $51,720.00 $0.00 $0.00
Project Total $568,920.00   $517,200.00 $51,720.00 $0.00 $0.00

CANADIAN 06/2009 2675504 STP -STIM (417) AG CT ST RESURFACE PIEDMONT ARRA: PIEDMONT RD FROM ARROWHEAD ST (192) TO APACHE ST (206) 1 $247,500.00 0L230 $0.00 $22,500.00 $0.00 $0.00
0C230 $225,000.00 $0.00 $0.00 $0.00
Project Total $247,500.00   $225,000.00 $22,500.00 $0.00 $0.00

CLEVELAND 06/2009 2664004 STP -STIM (236) AG CT ST TRAFFIC SIGNALS TRAFFIC SIGNAL UPGRADES & INTERCONNECT ON 24TH AVE WEST BEG @ SH-9 &EXT NORTH TO TECUMSEH RD, IN NORMAN 0 $660,000.00 0L230 $0.00 $60,000.00 $0.00 $0.00
0C230 $600,000.00 $0.00 $0.00 $0.00
Project Total $660,000.00   $600,000.00 $60,000.00 $0.00 $0.00

CLEVELAND 06/2009 2675104 STP -STIM (413) AG CT ST RESURFACE OKC ARRA: MULTIPLE LOCATIONS IN OKC ON SW 89TH, PENN, SW 119TH &MAY (PART IN OK COUNTY) 5 $2,970,000.00 0C230 $2,700,000.00 $0.00 $0.00 $0.00
0L230 $0.00 $270,000.00 $0.00 $0.00
Project Total $2,970,000.00   $2,700,000.00 $270,000.00 $0.00 $0.00

LOGAN / 2672804 STP -STIM (300) AG CO RD RESURFACE CASHION ARRA: COUNTY LINE RD, FROM SEWARD RD TO FOREST HILL RD 1 $247,500.00 0L230 $0.00 $22,500.00 $0.00 $0.00
0C230 $225,000.00 $0.00 $0.00 $0.00
Project Total $247,500.00   $225,000.00 $22,500.00 $0.00 $0.00

LOGAN / 2673704 STP -STIM (309) AG CO RD RESURFACE LOGAN CO. ARRA: PENNSYLVANIA FROM THE OK COUNTY LINE, NORTH 1.7 $600,000.00 0L230 $0.00 $50,640.00 $0.00 $0.00
0C230 $506,400.00 $0.00 $0.00 $0.00
09012 $0.00 $0.00 $0.00 $42,960.00
Project Total $600,000.00   $506,400.00 $50,640.00 $0.00 $42,960.00

OKLAHOMA 06/2009 2675004 STP -STIM (412) AG CT ST RESURFACE OKC ARRA: S. SHIELDS FROM SE 44TH TO SE 89TH & SE 89TH FROM SHIELDSTO I-35 3.5 $1,650,000.00 0C230 $1,500,000.00 $0.00 $0.00 $0.00
0L230 $0.00 $150,000.00 $0.00 $0.00
Project Total $1,650,000.00   $1,500,000.00 $150,000.00 $0.00 $0.00