Information source is the ODOT Construction Division Graybook system - Sun 9/16/2012 8:20:08 PM |
County | Highway Number |
Contract ID |
Job Piece |
Project | Stimulus Indicator |
Prime Contractor |
Job Description |
Current Contract Amount |
Amount Paid |
Let Date |
Award Date |
Contract Date |
Work Order Date |
Work Order Effective Date |
Estimated Completion Date |
Actual Completion Date |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Atoka | US-69 | 090309 | 2634404 | NH-STIM(150)(178)(179)3R | S | DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV | {AKA NHY-13N(133)(128)129)3R} 11.45 MI RESURF (CONC) US-69 BEG 1.4 MI N OF SH-75 EXT N / US-69 VAR LOCS PITTSBURG CO. | $5,339,316.57 | $5,339,316.61 | 03/19/2009 | 03/30/2009 | 04/02/2009 | 04/03/2009 | 04/20/2009 | 10/16/2009 | 10/21/2009 |
Beckham | I-40 | 090002 | 2437205 | IM-STIM(024) | S | THE CUMMINS CONSTRUCTION CO., INC. | 7.93 MI. RESURFACE (ASPHALT) I-40 BEGIN AT MILE MARKER 25 & EXTEND NORTHEAST TO MILE MARKER 33. | $14,401,468.86 | $14,441,757.53 | 03/24/2009 | 03/30/2009 | 04/13/2009 | 04/14/2009 | 04/27/2009 | 01/21/2010 | 10/14/2010 |
Beckham | IS-40 | 100022 | 2623906 | IM-STIM(527) | S | THE CUMMINS CONSTRUCTION CO., INC. | 2.047 MI. IS-40;RESURFACE (ASPHALT) FROM MILE MARKER 22.75 EXTEND EAST TO MILE MARKER 25.11. | $3,851,447.06 | $3,848,841.05 | 03/18/2010 | 04/12/2010 | 04/23/2010 | 04/26/2010 | 06/07/2010 | 10/04/2010 | 07/19/2011 |
Blaine | US-270 | 090113 | 2572604 | NH-STIM(241)3R | S | HASKELL LEMON CONSTRUCTION CO. | 7.92 MI. RESURFACE (ASPHALT) US-270 BEGIN 0.3 MI. WEST OF SH-58 NORTH & EXTEND EAST. | $2,935,966.08 | $2,935,966.08 | 05/14/2009 | 05/19/2009 | 05/27/2009 | 05/29/2009 | 10/30/2009 | ||
Bryan | US-69 | 090149 | 2629504 | NH-STIM(152)3R | S | R. K. HALL CONSTRUCTION, LTD. | {AKA NHY-13N(127)3R} 5.26 MI. RESURFACE (ASPHALT) US-69 BEGIN 0.2 MI. N. OF THE TEXAS STATE LINE & EXTEND NORTH. | $3,947,240.33 | $3,935,957.93 | 03/19/2009 | 03/30/2009 | 04/14/2009 | 04/30/2009 | 07/06/2009 | 09/18/2009 | 05/26/2010 |
Canadian | I-40 | 090310 | 2634104 | IM-STIM(154)(153)3R | S | HASKELL LEMON CONSTRUCTION CO. | {AKA IMY-40-4(427)115 3R/IMY-40-4(428)108 3R} 10.50 MI. RESURFACE (UTBWC) I-40 BEGIN AT MILE MARKER 108 & EXTEND E. | $2,769,378.76 | $2,745,906.40 | 03/19/2009 | 03/30/2009 | 04/06/2009 | 04/07/2009 | 07/06/2009 | 09/18/2009 | 10/15/2009 |
Canadian | I-40 | 090321 | 2053904 | IMY-040-4(396)128SS/IM-* | X | DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV | *STIM(15)/IMG-40-4(421)TR 7.39 MI. RECONSTRUCT (ADDED LANE), BRIDGE & SAFTEY IMPROVEMENT I-40 FROM M.M. 124 TO M.M. 136. | $62,173,001.55 | $62,172,980.96 | 03/19/2009 | 03/30/2009 | 04/03/2009 | 04/07/2009 | 06/01/2009 | 08/09/2011 | 10/25/2011 |
Canadian | SH-3 | 090171 | 2635504 | NH-STIM(238)3R | S | VANCE BROTHERS, INC. | SH-3 BEGIN .36 MILES SOUTH OF THE KINGFISHER C/L EXTEND SE | $2,554,202.01 | $2,493,452.00 | 05/14/2009 | 05/19/2009 | 06/03/2009 | 06/05/2009 | 10/30/2009 | 01/20/2010 | |
Carter | US-70 | 090221 | 2640304 | NH-STIM(121)3R | S | SEAL MASTERS, INC. | 8.00 MI. RESURFACE (ASPHALT) & GUARDRAIL US-70 BEGIN 2.67 MI. EAST OF I-35 & EXTEND EAST. | $3,965,364.96 | $3,839,899.95 | 05/14/2009 | 05/19/2009 | 06/08/2009 | 06/09/2009 | 07/21/2010 | ||
Carter | US-70 | 090279 | 0924714 | STP-STIM(038)(040) | S | SILVER STAR CONSTRUCTION COMPANY, INC. | 3.367 MI. GRD., DRN., SURF., & BR. US-70 BEG. AT JEFFERSON C/L EXT. E./OVER RED OAK CRK. 1.8 MI. E. OF JEFFERSON C/L. | $7,403,893.04 | $7,372,335.03 | 03/19/2009 | 03/30/2009 | 04/15/2009 | 04/16/2009 | 04/27/2009 | 12/22/2009 | 08/15/2012 |
Cimarron | US-287 | 090496 | 2313204 | NH-STIM(428) | S | HIGHWAY CONTRACTORS, INC. | 0.829 MI. GRADE, DRAIN & SURFACE BEGIN 7.0 MIILES SOUTH OF US-64 AND EXTEND SOUTH. | $2,418,007.75 | $2,416,578.79 | 06/18/2009 | 06/22/2009 | 07/07/2009 | 07/10/2009 | 08/17/2009 | 02/12/2010 | 06/07/2010 |
Cimarron | US-64 | 090116 | 2628204 | NH-STIM(299)3R/NH-STIM* | S | HIGHWAY CONTRACTORS, INC. | *(031)/ 14.462 MI.;US-64 RESURFACE(ASPHALT)BEGIN AT US-287 SO. & EXTEND E. FROM 7.5 MI. E. OF SH-56. | $8,896,669.16 | $8,844,205.02 | 05/14/2009 | 05/19/2009 | 06/08/2009 | 06/09/2009 | 10/30/2009 | 12/31/2009 | |
Cleveland | I-44 | 090003 | 2195005 | IM-STIM(013) | S | HASKELL LEMON CONSTRUCTION CO. | 7.170 MI. PAVEMENT REHABILITATION AND BRIDGE REPAIR I-44 FROM US-62 EXTEND NORTH. | $7,975,888.27 | $7,970,684.48 | 03/24/2009 | 03/30/2009 | 04/06/2009 | 04/08/2009 | 04/27/2009 | 09/23/2009 | 08/31/2009 |
Comanche | I-44 | 090497 | 2031304 | IM-STIM(296) | S | ALLEN CONTRACTING, INC. | 2.545 MI. GRADE, DRAIN, SURFACE & BRIDGE I-44 FROM 1.6 MI. N. OF SH-7 EXTEND NORTH. | $16,230,834.98 | $15,378,823.47 | 06/18/2009 | 06/22/2009 | 06/30/2009 | 07/22/2009 | 08/24/2009 | 08/18/2010 | |
Comanche | SH-7 | 090311 | 1043907 | STP-STIM(037) | S | PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV) | 0.381 MI. GRADE, DRAIN, SURFACE & BRIDGE SH-7 OVER BEAVER CRK. 2.44 MI. W. OF COMANCHE / STEPHENS COUNTY LINE. | $2,402,227.86 | $2,295,835.44 | 03/19/2009 | 03/30/2009 | 04/08/2009 | 04/13/2009 | 04/27/2009 | 12/02/2009 | 12/31/2010 |
Custer | US-183 | 090175 | 2636605 | NH-STIM(069)(70)3R | S | CASWELL CONTRACTING, INC. | 10.62 MI. RESURFACE (ASPHALT) US-183 BEGIN 0.33 MILE NORTH OF THE SH-33 EAST JUNCTION AND EXTEND NORTH. | $2,276,100.63 | $2,276,100.64 | 05/14/2009 | 05/19/2009 | 06/22/2009 | 06/24/2009 | 10/30/2009 | ||
Ellis | US-283 | 090312 | 2094307 | STP-STIM(034) | S | PLAINS BRIDGE CONTRACTING OF OK.,LLC & TREAS CONST. INC.(JV) | 0.692 MI. GRADE, DRAIN, SURFACE & BRIDGE US-283 OVER TWENTY-FIVE MILE CRK. 0.5 MI. N. OF SH-15 JCT. | $3,601,663.25 | $3,517,703.68 | 03/19/2009 | 03/30/2009 | 04/09/2009 | 04/13/2009 | 04/27/2009 | 11/22/2009 | 11/10/2011 |
Garfield | US-60 | 090176 | 2635704 | NH-STIM(239)3R | S | THE CUMMINS CONSTRUCTION CO., INC. | 5.00 MI. RESURFACE (ASPHALT) US-60 BEGIN AT THE MAJOR COUNTY LINE AND EXTEND EAST. | $2,562,637.73 | $2,562,637.73 | 05/14/2009 | 05/19/2009 | 06/01/2009 | 06/05/2009 | 10/30/2009 | 11/11/2009 | |
Garfield | US-81 | 100200 | 1496004 | NH-STIM(528) | S | HASKELL LEMON CONSTRUCTION CO. | 7.00 MI. US-81;GRADE,DRAIN & SURFACE;FROM THE KINGFISHER/GARFIELD C/L, EXTEND NORTH. | $3,915,746.37 | $3,912,674.82 | 03/18/2010 | 04/12/2010 | 04/21/2010 | 04/27/2010 | 08/02/2010 | 01/28/2011 | 06/07/2011 |
Garvin | I-35 | 090326 | 2097006 | IM-STIM(010) | S | DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV | 6.50 MI. RESURFACE (CONCRETE) I-35 FROM SH-29 EXTEND NORTH TO SH-19. | $29,001,884.35 | $29,006,315.12 | 03/24/2009 | 03/30/2009 | 04/03/2009 | 04/07/2009 | 04/27/2009 | 11/27/2010 | 12/14/2010 |
Garvin | SH-76 | 090118 | 2629404 | STP-STIM(156)3R | S | THE CUMMINS CONSTRUCTION CO., INC. | {AKA STPY-125C(172)3R} 8.01 MI. RESURFACE (ASPHALT) BEGIN AT THE CARTER COUNTY LINE & EXTEND NORTH. | $1,171,855.42 | $1,164,745.71 | 03/19/2009 | 03/30/2009 | 04/13/2009 | 04/15/2009 | 07/06/2009 | 08/09/2009 | 07/10/2009 |
Haskell | SH-9 | 090210 | 2635204 | STP-STIM(157)(158)3R/NH-* | S | CHESTER BROSS CONSTRUCTION COMPANY/C.B. EQUIPMENT, INC. | *STIM(159)(163)(164)3R {AKA STPY-131B(97)151B(205)3R/NHY-13N(136)(137)14N(81)3R} 13.85 MI PAVE REHAB VAR LOCS DIV 1. | $3,886,458.51 | $3,886,458.52 | 03/19/2009 | 03/30/2009 | 04/09/2009 | 04/15/2009 | 04/27/2009 | 11/22/2009 | 04/05/2010 |
Hughes | US-270B | 090119 | 2492804 | STP-STIM(172)3R | S | GLOVER & ASSOCIATES, INC. | {AKA STPY-132B(113)3R} 1.96 MI. RESURFACE (ASPHALT) & REHAB. US-270B BEGIN AT SH-48 AND EXTEND EAST. | $412,196.20 | $411,227.02 | 03/19/2009 | 03/30/2009 | 04/07/2009 | 04/08/2009 | 07/06/2009 | 08/04/2009 | 09/02/2009 |
Jackson | US-62 | 090313 | 2636704 | NH-STIM(71)(86)(87)3R | S | DOBSON BROTHERS CONSTRUCTION CO. | 17.62 MI RESURF (ASPH) US-62 BEG 2.37 MI E US-283 & EXT E (W.BOUND ONLY)/BEG TILLMAN C/L EXT E (W.BOUND ONLY). | $3,407,802.50 | $3,407,246.38 | 03/19/2009 | 03/30/2009 | 04/13/2009 | 04/17/2009 | 06/01/2009 | 09/08/2009 | 09/30/2009 |
Kay | I-35 | 090314 | 2443207 | IM-STIM(019) | S | KOSS CONSTRUCTION COMPANY & SUBSIDIARY | 4.918 MI. GRADE, DRAIN, SURFACE, BRIDGE & CABLE BARRIER I-35 BEGIN AT M.M. 224.43 & EXTENDN. TO M.M. 229.33. | $25,087,576.99 | $25,087,576.99 | 03/19/2009 | 03/30/2009 | 04/08/2009 | 04/24/2009 | 06/01/2009 | 03/02/2011 | 08/15/2011 |
Le Flore | US-271 | 090292 | 1139512 | NH-STIM(008) | S | MANHATTAN ROAD & BRIDGE CO. | 1.522 MI. GRADE, DRAIN, SURFACE & BRIDGE US-271 FROM SH-112 EXTEND WEST TO SH-9A. | $6,867,057.98 | $6,867,058.00 | 06/18/2009 | 06/22/2009 | 07/08/2009 | 07/09/2009 | 09/14/2009 | 09/13/2010 | 08/18/2011 |
Le Flore | US-59 | 090406 | 1712705 | NH-STIM(169) | S | KOSS CONSTRUCTION COMPANY & SUBSIDIARY | 8.006 KM GRADE, DRAIN, SURFACE & BRIDGE US-59 FROM SH-9 EXTEND NORTH. | $20,728,271.97 | $20,162,717.80 | 04/23/2009 | 04/27/2009 | 05/13/2009 | 05/28/2009 | 09/08/2009 | 11/01/2010 | 11/17/2011 |
Lincoln | SH-105 | 090121 | 2629304 | STP-STIM(173)3R | S | THE QUAPAW COMPANY | {AKA STPY-141C(203)3R} 7.970 MI. RESURFACE (ASPHALT) SH-105 BEGIN AT US-177 AND EXTEND EAST. | $1,025,390.16 | $1,020,332.44 | 03/24/2009 | 03/30/2009 | 04/08/2009 | 04/09/2009 | 07/06/2009 | 08/04/2009 | 09/22/2009 |
Lincoln | SH-18 | 090120 | 2492904 | STP-STIM(174)3R | S | THE QUAPAW COMPANY | {AKA STPY-141C(187)3R} 5.05 MI. RESURFACE (ASPHALT) SH-18 BEGIN AT SH-105 & EXTEND NORTH. | $502,640.24 | $491,515.77 | 03/24/2009 | 03/30/2009 | 04/08/2009 | 04/09/2009 | 07/06/2009 | 08/04/2009 | 09/22/2009 |
Major | US-281 | 100091 | 2406804 | STP-STIM(519) | S | SEWELL BROS., INC. | 0.491 MI. US-281;BRIDGE & APPROACHES,OVER GRIEVER CR., 5.0 MI. NORTH OF US-60E. | $3,038,474.32 | $2,682,426.96 | 03/18/2010 | 04/12/2010 | 04/26/2010 | 05/03/2010 | 08/02/2010 | 05/03/2011 | 09/05/2012 |
Mayes | US-69 | 090152 | 2628304 | NH-STIM(175)3R | S | PENHALL COMPANY | {AKA NHY-13N(126)3R} 6.190 MI. PAVEMENT REHABILITATION (DOWEL BAR RETROFIT) US-69 BEGIN AT SH-28 & EXTEND NORTH. | $1,893,658.44 | $1,893,658.44 | 03/19/2009 | 03/30/2009 | 04/10/2009 | 04/14/2009 | 06/01/2009 | 09/28/2009 | 12/04/2009 |
Murray | I-35 | 090225 | 2640204 | IM-STIM(120)3R | S | SILVER STAR CONSTRUCTION COMPANY, INC. | 6.56 MI. RESURFACE (ASPHALT) I-35 BEGIN @ THE CARTER COUNTY LINE & EXTEND NORTH. | $5,378,142.38 | $5,368,935.82 | 03/24/2009 | 03/30/2009 | 04/15/2009 | 04/16/2009 | 04/27/2009 | 07/20/2009 | 09/30/2010 |
Muskogee | I-40 | 090323 | 2090005 | IM-STIM(001) | S | DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV | 4.998 MI. PAVEMENT REHABILITATION & BRIDGE I-40 FROM MILE MARKER 281.67 TO 288.22. | $34,641,051.48 | $32,962,462.82 | 03/19/2009 | 03/30/2009 | 04/03/2009 | 04/07/2009 | 06/01/2009 | 01/21/2011 | 03/30/2012 |
Noble | I-35 | 090124 | 2628004 | IM-STIM(176)3R | S | EVANS & ASSOCIATES CONSTRUCTION CO., INC. | {AKA IMY-35-4(236)179 3R} 6.01 MI. RESURFACE (UTBWC) I-35 BEGIN 1.2 MI. N. OF THE PAYNE COUNTY LINE & EXTEND NORTH. | $1,293,326.64 | $1,293,326.65 | 03/19/2009 | 03/30/2009 | 04/15/2009 | 04/16/2009 | 07/06/2009 | 08/19/2009 | 09/03/2009 |
Noble | I-35 | 090301 | 2028404 | IM-STIM(237) | S | DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV | 5.567 MI. GRADE, DRAIN, SURFACE, BRIDGE & CABLE BARRIER I-35 FROM MILE MARKER 198 TO MILE MARKER 203. | $13,602,863.28 | $13,602,863.27 | 04/23/2009 | 04/27/2009 | 05/11/2009 | 05/13/2009 | 09/08/2009 | 12/21/2010 | 12/28/2011 |
Nowata | US-169 | 090281 | 2440705 | NH-STIM(062) | S | APAC-CENTRAL, INC. | 6.197 MI. WIDEN & RESURFACE US-169 BEGIN 6.0 MI. S. OF THE KANSAS STATE LINE & EXTEND N. TO THE KANSAS STATE LINE. | $3,613,693.79 | $3,613,693.81 | 03/19/2009 | 03/30/2009 | 04/13/2009 | 04/15/2009 | 07/06/2009 | 09/03/2009 | 11/10/2009 |
Okfuskee | I-40 | 090193 | 2638304 | IM-STIM(093)3R | S | APAC-CENTRAL, INC. | 6.91 MI. RESURFACE (ASPHALT) I-40 FROM SEMINOLE COUNTY LINE & EXTEND EAST. | $3,610,605.52 | $3,570,770.85 | 05/14/2009 | 05/19/2009 | 06/08/2009 | 06/09/2009 | 10/30/2009 | 12/04/2009 | |
Oklahoma | I-235 | 090125 | 2628104 | IM-STIM(177)3R | S | PENHALL COMPANY | {AKA IMY-235-3(104)0003R} 3.47 MI. PAVEMENT REHAB.(DOWEL BAR RETROFIT) I-235 BEGIN AT N. END OKLA. RVR. BR. & EXTEND N. | $2,681,598.80 | $2,631,598.80 | 03/24/2009 | 03/30/2009 | 04/10/2009 | 04/13/2009 | 04/27/2009 | 07/25/2009 | 08/31/2009 |
Okmulgee | I-40 | 110492 | 2090805 | IMY-0040-6(370)233/IMY-* | S | DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV | 6.34 MI. I-40: PAVEMENT REHABILITATION AND BRIDGE PAINTING; FROM US-75 EXTEND EAST. | $24,656,790.59 | $12,527,334.84 | 10/20/2011 | 11/07/2011 | 11/17/2011 | 11/28/2011 | 01/09/2012 | 09/21/2013 | |
Osage | SH-99 | 090457 | 2671004 | STP-STIM(291)3R | S | EVANS & ASSOCIATES CONSTRUCTION CO., INC. | 4.17 MI. SH-99;RESURFACE (ASPHALT)BEGIN JUST N. OF SH- 20, AND EXTEND NORTH.EXTEND NORTH 4.17 MI. | $628,511.67 | $619,772.58 | 05/14/2009 | 05/19/2009 | 06/03/2009 | 06/08/2009 | 07/06/2009 | 08/05/2009 | 06/10/2010 |
Osage | US-60 | 090456 | 2670904 | STP-STIM(290)3R | S | EVANS & ASSOCIATES CONSTRUCTION CO., INC. | 4.44 MI.;US-60;RESURFACE ( ASPHALT)BEGIN AT THE KAY C/L, EXTEND EAST. | $1,198,053.61 | $1,183,438.86 | 05/14/2009 | 05/19/2009 | 06/03/2009 | 06/05/2009 | 07/06/2009 | 07/28/2009 | 02/07/2012 |
Pawnee | US-64 | 090461 | 2671204 | STP-STIM(293)3R/NH-STIM* | S | CHESTER BROSS CONSTRUCTION COMPANY/C.B. EQUIPMENT, INC. | (294)3R. 14.35 MI. RESURFACE (CONCRETE) US-64 BEGIN AT SH-99 & EXT. E. / US-64/US-412 BEGIN AT JCT. SH-48 & EXT. E. | $3,784,543.68 | $3,766,421.61 | 05/14/2009 | 05/19/2009 | 06/08/2009 | 07/17/2009 | 08/17/2009 | 12/14/2009 | 09/23/2010 |
Pottawatomie | I-40 | 090198 | 2638404 | IM-STIM(095)(096)3R | S | HASKELL LEMON CONSTRUCTION CO. | 14.18 MI. RESURFACE (UTWBC) FROM SH-18 EXTEND EAST TO THE SEMINOLE COUNTY LINE. | $2,498,152.03 | $2,498,152.04 | 03/19/2009 | 03/30/2009 | 04/06/2009 | 04/07/2009 | 07/06/2009 | 08/19/2009 | 08/06/2009 |
Pushmataha | SH-3 | 090226 | 2024911 | NH-STIM(009) | S | THE CUMMINS CONSTRUCTION CO., INC. | 1.820 MI. GRADE, DRAIN & SURFACE SH-3 BEGIN EAST OF NS-406 & EXTEND EAST. | $4,056,079.21 | $4,170,271.14 | 03/24/2009 | 03/30/2009 | 04/13/2009 | 04/14/2009 | 04/27/2009 | 11/22/2009 | 08/13/2010 |
Rogers | SH-266 | 090328 | 2628404 | STP-STIM(180)3R/NH-STIM* | S | APAC-CENTRAL, INC. | *(88)3R {AKA STPY-166C(233)3R/NH-STIM(88)3R} 10.59 MI RESURF(ASPH) US-412 BEG AT MCCLELLAN KERR NAV CHANNEL & EXT E. | $2,434,397.70 | $2,434,397.70 | 03/24/2009 | 03/30/2009 | 04/14/2009 | 04/15/2009 | 07/06/2009 | 10/03/2009 | 11/30/2009 |
Seminole | I-40 | 090182 | 1362606 | IM-STIM(011) | S | KOSS CONSTRUCTION COMPANY & SUBSIDIARY | 2.473 MI. RECONSTRUCT (CONCRETE) - NO ADDED LANES I-40 FROM 4.0 MI. E. OF SH-99 & EXTEND EAST. | $9,724,011.03 | $9,553,646.00 | 05/14/2009 | 05/19/2009 | 06/03/2009 | 06/12/2009 | 07/13/2009 | 01/28/2010 | 01/27/2010 |
Seminole | IS-40 | 100253 | 1362607 | IMY-40-5(415)206/HSIPIG* | S | DUIT CONSTRUCTION COMPANY, INC./TTK CONSTRUCTION CO., INC JV | *-40-5(405)203TR/ 6.016 MI. IS-40;PAVEMENT REHAB. & CABLE BARRIER;FROM MILE MARKER 203, EXTEND E. TO MILE MARKER 213. | $25,265,282.38 | $23,158,814.45 | 08/19/2010 | 09/07/2010 | 09/20/2010 | 09/27/2010 | 01/03/2011 | 03/27/2012 | 04/30/2012 |
Seminole | SH-56 | 090128 | 2493104 | STP-STIM(181)3R | S | THE CUMMINS CONSTRUCTION CO., INC. | {AKA STPY-167C(147)3R} 4.76 MI. RESURFACE (ASPHALT) SH-56 BEGIN 5.1 MI. E. OF SH-99 & EXTEND EAST. | $952,088.05 | $954,546.25 | 03/19/2009 | 03/30/2009 | 04/13/2009 | 04/15/2009 | 07/06/2009 | 09/03/2009 | 02/19/2010 |
Sequoyah | I-40 | 090123 | 2627704 | IM-STIM(295)3R | S | GLOVER & ASSOCIATES, INC. | 4.39 MI. RESURFACE (ASPHALT) I-40 BEG. 0.53 MI. W. OF W. END ARK. RVR. BR. & EXT. E./SH-10 FROM S. RAMP I-40 & EXT. N. | $2,338,590.71 | $2,335,025.41 | 05/14/2009 | 05/19/2009 | 06/01/2009 | 06/05/2009 | 10/30/2009 | 12/31/2009 | |
Stephens | US-81 | 090317 | 2031618 | NH-STIM(039) | S | OBC, INC. | 0.441 MI. GRADE, DRAIN, SURFACE & BRIDGE US-81 BYPASS AT AT BOIS D'ARC AVE. 1.5 MI. W. OF US-81. | $5,529,375.89 | $5,507,634.93 | 03/19/2009 | 03/30/2009 | 04/02/2009 | 04/03/2009 | 06/01/2009 | 02/25/2010 | 06/15/2011 |
Texas | US-412 | 090319 | 2624006 | NH-STIM(028) | S | DOBSON BROTHERS CONSTRUCTION CO. | 7.050 MI. RESURFACE (ASPHALT) US-412 FROM 0.12 MI. E. OF US-54 EXTEND EAST. | $6,439,489.62 | $6,463,239.96 | 03/19/2009 | 03/30/2009 | 04/08/2009 | 04/13/2009 | 04/27/2009 | 09/23/2009 | 07/02/2010 |
Texas | US-54 | 090201 | 2636404 | NH-STIM(065)(66)3R | S | APAC-KANSAS, INC. | 8.60 MI. RESURFACE (ASPHALT) US-54 BEGIN 9.8 MI. N.E. OF THE TEXAS STATE LINE AND EXTEND NORTHEAST. | $2,312,809.69 | $2,237,052.01 | 03/19/2009 | 03/30/2009 | 04/10/2009 | 04/28/2009 | 07/06/2009 | 09/03/2009 | 11/22/2010 |
Texas | US-54 | 090219 | 1497138 | NH-STIM(064)3R | S | APAC-KANSAS, INC. | 5.00 MI. RESURFACE (ASPHALT) US-54 BEGIN 5.3 MI. SOUTHWEST OF THE SH-94 JCT. & EXTEND NORTHEAST. | $1,196,508.80 | $1,195,097.18 | 06/18/2009 | 06/22/2009 | 07/02/2009 | 07/22/2009 | 10/30/2009 | 06/30/2010 | |
Texas | US-64 | 090290 | 2636107 | NH-STIM(033) | S | J & R SAND COMPANY, INC. | 4.458 MI. RESURFACE (ASPHALT) US-64 FROM THE TEXAS/CIMARRON COUNTY LINE EXTEND EAST. | $3,613,398.05 | $3,634,624.91 | 03/19/2009 | 03/30/2009 | 04/08/2009 | 04/13/2009 | 04/27/2009 | 09/03/2009 | 10/05/2009 |
Tillman | US-183 | 090129 | 2604005 | STP-STIM(182)3R | S | T & G CONSTRUCTION, INC. | {AKA STPY-171B(131)3R} 3.95 MI RESURF (ASPH) US-183/US-70 BEG 8.0 MI N OF TEXAS ST LN & EXT N TO S EDGE OF FREDRICK. | $733,135.42 | $733,135.42 | 03/24/2009 | 03/30/2009 | 04/13/2009 | 04/17/2009 | 07/06/2009 | 08/04/2009 | 08/28/2009 |
Tulsa | I-244 | 090329 | 2636205 | IM-STIM(048)(49)(50)(47) | S | MANHATTAN ROAD & BRIDGE CO. & SHERWOOD CONSTRUCTION CO, INC. | 5.805 MI. PAVEMENT REHAB, BRIDGE, TRAFFIC LIGHTING & TRAFFIC SIGNS I-244 AT VARIOUS LOCATIONS IN DIVISION 8. | $69,004,891.61 | $69,258,169.15 | 04/23/2009 | 04/27/2009 | 05/13/2009 | 06/01/2009 | 06/08/2009 | 01/08/2011 | |
Tulsa | SH-151 | 090322 | 2316607 | STP-STIM(061) | S | MANHATTAN ROAD & BRIDGE CO. | 0.492 MI. GRADE, DRAIN, SURFACE & BRIDGE SH-151 OVER SH-51 & OVER SL&SF RR 1.5 MI. EAST OF THE CREEK C/L. | $7,512,536.00 | $7,512,535.99 | 03/19/2009 | 03/30/2009 | 04/13/2009 | 04/14/2009 | 06/01/2009 | 03/27/2010 | 07/02/2010 |
Washita | US-183 | 090110 | 1712604 | NH-STIM(240)SS | S | VENTURE CORPORATION DBA V. C. O. PAVING | 2.489 MI. GRADE, DRAIN, SURFACE, BRIDGE & EROSION CONTROL US-183 FROM 2.8 MI. S.W. OF SH-152 & EXTEND N.E. | $5,476,140.44 | $5,472,151.65 | 04/23/2009 | 04/27/2009 | 05/13/2009 | 07/02/2009 | 08/03/2009 | 01/19/2010 | 08/16/2010 |
Woods | SH-45 | 090205 | 2636504 | STP-STIM(067)(063)3R | S | THE CUMMINS CONSTRUCTION CO., INC. | 7.20 MI. RESURF.(ASPH.) US-281 BEG. 4.5 MI. N. OF MAJOR C/L & EXT. S. / SH-45 BEG. 4.6 MI. E. OF US-281 & EXT. E. | $1,343,200.51 | $1,344,488.68 | 03/24/2009 | 03/30/2009 | 04/13/2009 | 04/14/2009 | 07/06/2009 | 08/24/2009 | 12/04/2009 |