Contract ID: | 180355 | Estimate Number: | 0012 | Contract No: | 500348 | |||
Residency: | ANADARKO RESIDENCY (07300) | Estimate Type: | Progressive | Account No: | 400700 | |||
Project Number(s): | STP-126C(063) | ||||||||||||
Primary Job Piece No: | 20301(04) | ||||||||||||
Contract Description: | GRADE, DRAIN, SURFACE, AND BRIDGE SH-37: FROM 0.7 MILES EAST OF THE US-81 JUNCTION, EXTEND EAST NEAR MINCO. PROJECT LENGTH = 3.929 MILES | ||||||||||||
Primary County: | GRADY | ||||||||||||
Name of Road: | SH-37 | ||||||||||||
Prime Contractor: | THE CUMMINS CONSTRUCTION CO., INC. | ||||||||||||
P. O. BOX 748 | |||||||||||||
ENID , OK 73702 | |||||||||||||
Surety Company: | HARTFORD ACCIDENT & INDEMNITY COMPANY | ||||||||||||
Date Let: | 04/18/2019 | NTP Effective Date: | 09/09/2019 | Pay Period: | 12/01/2021 TO 12/15/2021 |
Date Awarded: | 05/06/2019 | Date Work Began: | 06/14/2021 | Original Contract Time: | 300 |
Date Contract Executed: | 05/22/2019 | Date Time Stopped: | Current Time Charged: | 125.00 | |
Date NTP Issued: | 05/28/2019 | Completion Date: | Current Time Allowed: | 300.00 | |
General Liability Expires: | 09/01/2022 | Workman's Comp Expires: | 01/01/2022 | Percent Time Used: | 41.67 % |
Specification Year: | 2009 | Date Approved: | 12/20/2021 | ||
Bid Amount: | $11,770,834.83 | Total to Date | Prev to Date | This Estimate | |||
Funds Available (Bid + Positive C/O): | $11,787,394.83 | Participating: | $3,476,418.77 | $2,759,477.83 | $716,940.94 | ||
Percent Complete: | 29.64 % | Non Participating: | $0.00 | $0.00 | $0.00 | ||
Unearned Balance: | $8,293,938.46 | Total Earnings: | $3,476,418.77 | $2,759,477.83 | $716,940.94 | ||
Stockpiled Materials: | $13,293.80 | $14,191.16 | $-897.36 | ||||
Gross Earnings: | $3,489,712.57 | $2,773,668.99 | $716,043.58 | ||||
Other Adjustments: | $3,743.80 | $2,124.30 | $1,619.50 | ||||
Liq Dam/Disincentive: | $0.00 | $0.00 | $0.00 | ||||
TOTAL: | $3,493,456.37 | $2,775,793.29 | $717,663.08 |
Contract ID: | 180355 | Estimate Number: | 0012 | Primary JP: | 20301(04) | |||
CHANGE ORDER HISTORY | |||||
Change Order Nbr. | Change Order Description | Status | Approval Date | Contract Time Adjustment | Total Change Order Amount |
001 | Change Start to WOrk Date | Approved | 02/02/2021 | 0.0 | $0.00 |
002 | Add Police | Approved | 09/22/2021 | 0.0 | $16,560.00 |
STOCKPILE PAYMENT HISTORY | |||||
Project | Line Nbr | Stockpile Description | Adjustment Type | Estimate Nbr | Adjusted Amount |
20301(04) | 0032 | STR-CV/DR (AML) | Stockpiled Material Initial Payment | 0004 | $5,187.77 |
20301(04) | 0032 | STR-CV/DR (AML) | Stockpiled Material Initial Payment | 0004 | $1,729.25 |
20301(04) | 0032 | SSTL FABS (AML) | Stockpiled Material Initial Payment | 0005 | $766.50 |
20301(04) | 0033 | PIPE-CV/DR (AML) | Stockpiled Material Adjustment | 0011 | $-548.90 |
20301(04) | 0033 | PIPE-CV/DR (AML) | Stockpiled Material Initial Payment | 0004 | $548.90 |
20301(04) | 0033 | PIPE-CV/DR (AML) | Stockpiled Material Initial Payment | 0004 | $914.82 |
20301(04) | 0033 | PIPE-CV/DR (AML) | Stockpiled Material Adjustment | 0011 | $-914.82 |
20301(04) | 0034 | PIPE-CV/DR (AML) | Stockpiled Material Initial Payment | 0004 | $3,159.53 |
20301(04) | 0034 | PIPE-CV/DR (AML) | Stockpiled Material Adjustment | 0010 | $-3,159.53 |
20301(04) | 0035 | PIPE-CV/DR (AML) | Stockpiled Material Initial Payment | 0004 | $8,568.19 |
20301(04) | 0035 | PIPE-CV/DR (AML) | Stockpiled Material Adjustment | 0007 | $-8,568.19 |
20301(04) | 0036 | PIPE-CV/DR (AML) | Stockpiled Material Adjustment | 0007 | $-3,132.74 |
20301(04) | 0036 | PIPE-CV/DR (AML) | Stockpiled Material Initial Payment | 0004 | $3,828.90 |
20301(04) | 0037 | PIPE-CV/DR (AML) | Stockpiled Material Adjustment | 0007 | $-4,468.02 |
20301(04) | 0037 | PIPE-CV/DR (AML) | Stockpiled Material Initial Payment | 0005 | $4,468.02 |
20301(04) | 0037 | PIPE-CV/DR (AML) | Stockpiled Material Initial Payment | 0005 | $4,980.26 |
20301(04) | 0037 | PIPE-CV/DR (AML) | Stockpiled Material Adjustment | 0007 | $-4,980.26 |
20301(04) | 0037 | PIPE-CV/DR (AML) | Stockpiled Material Adjustment | 0007 | $-4,980.26 |
20301(04) | 0037 | PIPE-CV/DR (AML) | Stockpiled Material Initial Payment | 0007 | $4,980.26 |
20301(04) | 0045 | PIPE-CMP | Stockpiled Material Adjustment | 0008 | $-1,410.14 |
20301(04) | 0045 | PIPE-CMP | Stockpiled Material Adjustment | 0012 | $-897.36 |
20301(04) | 0045 | PIPE-CMP | Stockpiled Material Initial Payment | 0004 | $7,221.62 |
20301(04) | 0046 | PIPE-CMP | Stockpiled Material Initial Payment | 0004 | $1,390.99 |
20301(04) | 0046 | PIPE-CMP | Stockpiled Material Adjustment | 0007 | $-1,390.99 |
20301(04) | 0047 | PIPE-CMP | Stockpiled Material Initial Payment | 0004 | $6,558.13 |
20301(04) | 0047 | PIPE-CMP | Stockpiled Material Adjustment | 0007 | $-6,558.13 | Subtotals For Stockpile Payments | $13,293.80 |
LIQUIDATED DAMAGES HISTORY | |||||||||
Adjustment Description | Estimate Nbr | Time Units | Rate | Adjustment Amount | |||||
No liquidated damages have been assessed on this contract. | Subtotals For Liquidated Damages | $ |
CONTRACT ADJUSTMENTS HISTORY | ||
Adjustment Description | Estimate Nbr | Adjustment Amount |
No general contract adjustments have been created on this contract. | Subtotals For Contract Adjustments | $0.00 |
LINE ITEM ADJUSTMENT HISTORY | |||||||
Project | Item Nbr | Line Item Description | Adjustment Type | Estimate Nbr | Adj Quantity | Unit Price | Adjusted Amount |
20301(04) | 0002 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0002 | 4,703.70 | $0.02 | $96.24 |
20301(04) | 0002 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0003 | 7,327.16 | $0.02 | $149.91 |
20301(04) | 0002 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0005 | 17,680.73 | $0.02 | $520.87 |
20301(04) | 0002 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0012 | 7,049.63 | $0.06 | $482.62 |
20301(04) | 0003 | UNCLASSIFIED BORROW | Fuel Price Adjustment | 0003 | 500.00 | $0.02 | $10.23 |
20301(04) | 0003 | UNCLASSIFIED BORROW | Fuel Price Adjustment | 0011 | 1,800.00 | $0.11 | $209.63 |
20301(04) | 0003 | UNCLASSIFIED BORROW | Fuel Price Adjustment | 0012 | 2,660.00 | $0.06 | $182.10 |
20301(04) | 0021 | SUPERPAVE, TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0010 | 964.37 | $0.16 | $158.98 |
20301(04) | 0021 | SUPERPAVE, TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0011 | 4,143.50 | $0.16 | $683.06 |
20301(04) | 0021 | SUPERPAVE, TYPE S3(PG 64-22 OK) | Asphalt Binder Adjustment | 0012 | 3,544.30 | $0.16 | $584.28 |
20301(04) | 0023 | SUPERPAVE, TYPE S4(PG 64-22 OK) | Asphalt Binder Adjustment | 0011 | 940.04 | $0.18 | $177.10 |
20301(04) | 0023 | SUPERPAVE, TYPE S4(PG 64-22 OK) | Asphalt Binder Adjustment | 0012 | 1,383.35 | $0.18 | $260.62 |
20301(04) | 0075 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0005 | 1,605.00 | $0.02 | $47.28 |
20301(04) | 0075 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0012 | 1,605.00 | $0.06 | $109.88 |
20301(04) | 0080 | UNCLASSIFIED EXCAVATION | Fuel Price Adjustment | 0005 | 2,410.00 | $0.02 | $71.00 | Subtotals For Line Item Adjustments | $3,743.80 |
MILESTONE INFORMATION | |||||||||
Milestone Number | Milestone Description | Start Date | End Date | Current Time Allowed | Rate | Milestone Closed | |||
No milestones exist for this contract. |
MILESTONE ADJUSTMENTS | |||||||||
Milestone Number | Milestone Adjustment Description | Estimate Nbr | Total | ||||||
No milestones adjustments exist for this contract. | Subtotals For Milestones | $ |
Contract ID: | 180355 | Estimate Number: | 0012 | Primary JP: | 20301(04) | |||
Line Item Number | Item Description | Item Number | Units | Bid Qty | Current Quantity | Quantity Paid This Est. | Quantity Paid To Date | Unit Price | Amount Paid This Est. | Amount Paid To Date |
Fed/State Project Number: STP-126C(063) | Project: 20301(04) | Category: 0100/ROADWAY | ||||||||
0001 | CLEARING AND GRUBBING | 201(A) 0102 | LSUM | 1.000 | 1.000 | 1.000 | $125,000.00 | $0.00 | $125,000.00 | |
0002 | UNCLASSIFIED EXCAVATION | 202(A) 0183 | CY | 124,475.000 | 124,475.000 | 7,049.630 | 62,111.680 | $8.90 | $62,741.71 | $552,793.95 |
0003 | UNCLASSIFIED BORROW | 202(D) 0184 | CY | 10,324.000 | 10,324.000 | 2,660.000 | 4,960.000 | $11.60 | $30,856.00 | $57,536.00 |
0004 | TYPE A-SALVAGED TOPSOIL | 205(A) 4229 | LSUM | 1.000 | 1.000 | 0.000 | 0.500 | $118,294.00 | $0.00 | $59,147.00 |
0005 | TEMPORARY SILT FENCE | 221(C) 2801 | LF | 5,000.000 | 5,000.000 | 2,421.000 | $1.20 | $0.00 | $2,905.20 | |
0006 | TEMPORARY SEDIMENT FILTER | 221(D) 2803 | EA | 3.000 | 3.000 | 0.000 | $80.00 | $0.00 | $0.00 | |
0007 | TEMPORARY SILT DIKE | 221(F) 0100 | LF | 2,716.000 | 2,716.000 | 1,960.000 | $5.50 | $0.00 | $10,780.00 | |
0008 | DITCH LINER PROTECTION | 229 4318 | LF | 14,460.000 | 14,460.000 | 0.000 | $1.10 | $0.00 | $0.00 | |
0009 | SOLID SLAB SODDING | 230(A) 2806 | SY | 319,105.000 | 319,105.000 | 0.000 | $1.30 | $0.00 | $0.00 | |
0010 | WATERING | 230(F) 2812 | KGAL | 25,529.000 | 25,529.000 | 0.000 | $3.00 | $0.00 | $0.00 | |
0011 | SEEDING METHOD B | 232(B) 2814 | AC | 65.930 | 65.930 | 0.000 | $250.00 | $0.00 | $0.00 | |
0012 | VEGETATIVE MULCHING | 233(A) 2817 | AC | 65.930 | 65.930 | 0.000 | $250.00 | $0.00 | $0.00 | |
0013 | MOWING | 241 2832 | AC | 131.860 | 131.860 | 0.000 | $50.00 | $0.00 | $0.00 | |
0014 | STABILIZED SUBGRADE | 307(K) 4300 | SY | 82,786.000 | 82,786.000 | 13,226.120 | $5.80 | $0.00 | $76,711.50 | |
0015 | TRAFFIC BOUND SURFACE COURSE TYPE E | 402(E) 0225 | TON | 1,778.000 | 1,778.000 | 0.000 | 1,040.710 | $31.50 | $0.00 | $32,782.38 |
0016 | TACK COAT | 407(B) 0250 | GAL | 26,309.000 | 26,309.000 | 0.000 | $3.00 | $0.00 | $0.00 | |
0017 | PRIME COAT | 408 5774 | GAL | 46,635.000 | 46,635.000 | 150.000 | $3.00 | $0.00 | $450.00 | |
0018 | FABRIC REINFORCEMENT | 409(A) 4242 | SY | 7,193.000 | 7,193.000 | 0.000 | $1.50 | $0.00 | $0.00 | |
0019 | BITUMINOUS BINDER | 409(B) 4268 | GAL | 1,798.000 | 1,798.000 | 0.000 | $4.00 | $0.00 | $0.00 | |
0020 | SUPERPAVE, TYPE S3(PG 70-28 OK) | 411(B) 5940 | TON | 9,248.000 | 9,248.000 | 0.000 | $77.00 | $0.00 | $0.00 | |
0021 | SUPERPAVE, TYPE S3(PG 64-22 OK) | 411(B) 5945 | TON | 45,656.000 | 45,656.000 | 3,544.300 | 8,652.170 | $70.60 | $250,227.58 | $610,843.20 |
0022 | SUPERPAVE, TYPE S4(PG 70-28 OK) | 411(C) 5955 | TON | 6,165.000 | 6,165.000 | 0.000 | $90.10 | $0.00 | $0.00 | |
0023 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 411(C) 5960 | TON | 9,515.000 | 9,515.000 | 1,383.350 | 2,323.390 | $74.10 | $102,506.24 | $172,163.20 |
0024 | SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 411(I) 6310 | TON | 500.000 | 500.000 | 0.000 | $105.40 | $0.00 | $0.00 | |
0025 | COLD MILLING PAVEMENT | 412 5267 | SY | 21,577.000 | 21,577.000 | 0.000 | $1.00 | $0.00 | $0.00 | |
0026 | STRUCTURAL EXCAVATION UNCLASSIFIED | 501(A) 0313 | CY | 109.000 | 109.000 | 76.120 | $30.00 | $0.00 | $2,283.60 | |
0027 | CLASS AA CONCRETE | 509(A) 0319 | CY | 204.000 | 204.000 | 45.140 | 203.290 | $534.00 | $24,104.76 | $108,556.86 |
0028 | CLASS C CONCRETE | 509(D) 0325 | CY | 2,576.000 | 2,576.000 | 42.000 | 63.000 | $243.00 | $10,206.00 | $15,309.00 |
0029 | REINFORCING STEEL | 511(A) 0332 | LB | 26,989.000 | 26,989.000 | 3,562.420 | 26,895.270 | $1.00 | $3,562.42 | $26,895.27 |
0030 | TYPE I PLAIN RIPRAP | 601(A) 0297 | TON | 313.000 | 313.000 | 0.000 | $49.00 | $0.00 | $0.00 | |
0031 | 6" CONCRETE DRIVEWAY | 610(B) 0604 | SY | 484.000 | 484.000 | 0.000 | $100.00 | $0.00 | $0.00 | |
0032 | INLET (SMD-TYPE 2) | 611(G) 6002 | EA | 2.000 | 2.000 | 0.000 | $3,000.00 | $0.00 | $0.00 | |
0033 | 24" R.C.PIPE CLASS III | 613(A) 0492 | LF | 64.000 | 64.000 | 0.000 | 54.000 | $59.00 | $0.00 | $3,186.00 |
0034 | 30" R.C.PIPE CLASS III | 613(A) 0493 | LF | 346.000 | 346.000 | 0.000 | 296.500 | $81.00 | $0.00 | $24,016.50 |
0035 | 48" R.C.PIPE CLASS III | 613(A) 0496 | LF | 118.000 | 118.000 | 0.000 | 128.000 | $164.00 | $0.00 | $20,992.00 |
0036 | 28" X 18" R.C.PIPE ARCH CLASS A-III | 613(A) 4496 | LF | 87.000 | 87.000 | 0.000 | 72.000 | $99.00 | $0.00 | $7,128.00 |
0037 | 36" X 22" R.C.PIPE ARCH CLASS A-III | 613(A) 4497 | LF | 723.000 | 723.000 | 0.000 | 344.000 | $121.00 | $0.00 | $41,624.00 |
0038 | 18" CORR. GALV. STEEL PIPE | 613(B) 0689 | LF | 1,080.000 | 1,080.000 | 0.000 | $26.00 | $0.00 | $0.00 | |
0039 | 24" CORR. GALV. STEEL PIPE | 613(B) 0690 | LF | 1,076.000 | 1,076.000 | 104.000 | 312.000 | $32.00 | $3,328.00 | $9,984.00 |
0040 | 30" CORR. GALV. STEEL PIPE | 613(B) 0691 | LF | 621.000 | 621.000 | 0.000 | $48.00 | $0.00 | $0.00 | |
0041 | 36" CORR. GALV. STEEL PIPE | 613(B) 0692 | LF | 48.000 | 48.000 | 0.000 | $53.00 | $0.00 | $0.00 | |
0042 | 42" CORR. GALV. STEEL PIPE | 613(B) 0693 | LF | 190.000 | 190.000 | 0.000 | $61.00 | $0.00 | $0.00 | |
0043 | 48" CORR. GALV. STEEL PIPE | 613(B) 0694 | LF | 22.000 | 22.000 | 0.000 | $79.00 | $0.00 | $0.00 | |
0044 | 60" CORR. GALV. STEEL PIPE | 613(B) 0696 | LF | 32.000 | 32.000 | 0.000 | $98.00 | $0.00 | $0.00 | |
0045 | 21" X 15" CORR. GALV. STEEL PIPE ARCH | 613(B) 4527 | LF | 992.000 | 992.000 | 42.000 | 108.000 | $29.00 | $1,218.00 | $3,132.00 |
0046 | 28" X 20" CORR. GALV. STEEL PIPE ARCH | 613(B) 4528 | LF | 1,132.000 | 1,132.000 | 40.000 | $35.00 | $0.00 | $1,400.00 | |
0047 | 35" X 24" CORR. GALV. STEEL PIPE ARCH | 613(B) 4529 | LF | 1,268.000 | 1,268.000 | 192.000 | 800.000 | $52.00 | $9,984.00 | $41,600.00 |
0048 | 6" PERFORATED PIPE UNDERDRAIN ROUND | 613(H) 0450 | LF | 500.000 | 500.000 | 0.000 | $21.25 | $0.00 | $0.00 | |
0049 | 6" NON-PERF.PIPE UNDERDRAIN RND. | 613(I) 1096 | LF | 100.000 | 100.000 | 0.000 | $13.75 | $0.00 | $0.00 | |
0050 | 36" X 22" PREFAB. CULVERT END SECTION, ARCH | 613(L) 4526 | EA | 2.000 | 2.000 | 2.000 | $800.00 | $0.00 | $1,600.00 | |
0051 | 24" PREFAB. CULVERT END SECTION, ROUND | 613(L) 5730 | EA | 2.000 | 2.000 | 0.000 | $750.00 | $0.00 | $0.00 | |
0052 | 30" PREFAB. CULVERT END SECTION, ROUND | 613(L) 5732 | EA | 2.000 | 2.000 | 0.000 | $845.00 | $0.00 | $0.00 | |
0053 | 48" PREFAB. CULVERT END SECTION, ROUND | 613(L) 5738 | EA | 4.000 | 4.000 | 4.000 | $2,280.00 | $0.00 | $9,120.00 | |
0054 | TYPE A4 CULVERT END TREATMENT | 613(M) 7186 | EA | 10.000 | 10.000 | 0.000 | $1,230.00 | $0.00 | $0.00 | |
0055 | TYPE B4 CULVERT END TREATMENT | 613(M) 7187 | EA | 20.000 | 20.000 | 0.000 | $1,540.00 | $0.00 | $0.00 | |
0056 | TYPE C4 CULVERT END TREATMENT | 613(M) 7188 | EA | 2.000 | 2.000 | 0.000 | $2,478.00 | $0.00 | $0.00 | |
0057 | TYPE D4 CULVERT END TREATMENT | 613(M) 7189 | EA | 2.000 | 2.000 | 0.000 | $3,026.00 | $0.00 | $0.00 | |
0058 | TYPE BB4 CULVERT END TREATMENT | 613(M) 7192 | EA | 10.000 | 10.000 | 0.000 | $2,822.00 | $0.00 | $0.00 | |
0059 | TYPE CC4 CULVERT END TREATMENT | 613(M) 7193 | EA | 4.000 | 4.000 | 0.000 | $4,160.00 | $0.00 | $0.00 | |
0060 | TYPE A6 CULVERT END TREATMENT | 613(M) 7196 | EA | 10.000 | 10.000 | 0.000 | $1,545.00 | $0.00 | $0.00 | |
0061 | TYPE B6 CULVERT END TREATMENT | 613(M) 7197 | EA | 20.000 | 20.000 | 0.000 | $2,162.00 | $0.00 | $0.00 | |
0062 | TYPE C6 CULVERT END TREATMENT | 613(M) 7198 | EA | 2.000 | 2.000 | 0.000 | $2,896.00 | $0.00 | $0.00 | |
0063 | TYPE D6 CULVERT END TREATMENT | 613(M) 7199 | EA | 2.000 | 2.000 | 0.000 | $4,162.00 | $0.00 | $0.00 | |
0064 | TYPE BB6 CULVERT END TREATMENT | 613(M) 7202 | EA | 10.000 | 10.000 | 0.000 | $3,600.00 | $0.00 | $0.00 | |
0065 | TYPE CC6 CULVERT END TREATMENT | 613(M) 7203 | EA | 4.000 | 4.000 | 0.000 | $4,742.00 | $0.00 | $0.00 | |
0066 | REMOVAL OF STRUCTURES & OBSTRUCTIONS | 619(A) 0920 | LSUM | 1.000 | 1.000 | 0.100 | 1.000 | $57,000.00 | $5,700.00 | $57,000.00 |
0067 | REMOVAL OF HEADWALL | 619(B) 0291 | EA | 8.000 | 8.000 | 6.000 | $1,800.00 | $0.00 | $10,800.00 | |
0068 | REMOVAL OF ASPHALT PAVEMENT | 619(B) 4728 | SY | 70,029.000 | 70,029.000 | 5,927.790 | 10,272.230 | $2.50 | $14,819.48 | $25,680.58 |
0069 | SAWING PAVEMENT | 619(C) 0924 | LF | 15,963.000 | 15,963.000 | 1,850.000 | 1,850.000 | $3.20 | $5,920.00 | $5,920.00 |
0070 | FENCE-STYLE SWF (5 BARBED WIRE) | 624(C) 4459 | LF | 15,460.000 | 15,460.000 | 2,151.000 | 3,944.000 | $5.00 | $10,755.00 | $19,720.00 |
0071 | MAILBOX INSTALLATION-SINGLE | 629(A) 4958 | EA | 8.000 | 8.000 | 0.000 | $100.00 | $0.00 | $0.00 | |
0072 | MAILBOX INSTALLATION-MULTIPLE | 629(B) 4959 | EA | 2.000 | 2.000 | 0.000 | $200.00 | $0.00 | $0.00 | |
0073 | MAILBOX | 629(C) 4960 | EA | 13.000 | 13.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
0074 | REMOVAL OF MAILBOX INSTALLATION | 629(D) 4961 | EA | 10.000 | 10.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
Subtotals For Category 0100/ROADWAY | $535,929.19 | $2,137,060.24 | ||||||||
Fed/State Project Number: STP-126C(063) | Project: 20301(04) | Category: 0200/BRIDGE 'A' - NBI NO. 10680 | ||||||||
0075 | UNCLASSIFIED EXCAVATION | 202(A) 1301 | CY | 1,605.000 | 1,605.000 | 1,605.000 | 3,210.000 | $5.00 | $8,025.00 | $16,050.00 |
0076 | STRUCTURAL EXCAVATION UNCLASSIFIED | 501(A) 1306 | CY | 255.000 | 255.000 | 255.000 | $30.00 | $0.00 | $7,650.00 | |
0077 | CLASS AA CONCRETE | 509(A) 1326 | CY | 527.000 | 527.000 | 0.000 | 527.000 | $369.20 | $0.00 | $194,568.40 |
0078 | REINFORCING STEEL | 511(A) 1332 | LB | 107,760.000 | 107,760.000 | 107,760.000 | $1.00 | $0.00 | $107,760.00 | |
0079 | REMOVAL OF BRIDGE ITEMS | 619(B) 2500 | LSUM | 1.000 | 1.000 | 0.500 | $8,000.00 | $0.00 | $4,000.00 | |
Subtotals For Category 0200/BRIDGE 'A' - NBI NO. 10680 | $8,025.00 | $330,028.40 | ||||||||
Fed/State Project Number: STP-126C(063) | Project: 20301(04) | Category: 0201/BRIDGE 'B' - NBI NO. 30770 | ||||||||
0080 | UNCLASSIFIED EXCAVATION | 202(A) 1301 | CY | 2,410.000 | 2,410.000 | 2,410.000 | $5.00 | $0.00 | $12,050.00 | |
0081 | STRUCTURAL EXCAVATION UNCLASSIFIED | 501(A) 1306 | CY | 380.000 | 380.000 | 0.000 | $30.00 | $0.00 | $0.00 | |
0082 | CLASS AA CONCRETE | 509(A) 1326 | CY | 780.300 | 780.300 | 206.340 | 457.970 | $326.75 | $67,421.60 | $149,641.70 |
0083 | REINFORCING STEEL | 511(A) 1332 | LB | 144,710.000 | 144,710.000 | 38,902.850 | 82,567.630 | $1.00 | $38,902.85 | $82,567.63 |
0084 | REMOVAL OF EXISTING BRIDGE STRUCTURE | 619(D) 1397 | LSUM | 1.000 | 1.000 | 0.500 | 0.500 | $8,000.00 | $4,000.00 | $4,000.00 |
Subtotals For Category 0201/BRIDGE 'B' - NBI NO. 30770 | $110,324.45 | $248,259.33 | ||||||||
Fed/State Project Number: STP-126C(063) | Project: 20301(04) | Category: 0300/TRAFFIC CONTROL | ||||||||
0085 | (SP)PORTABLE TRAFFIC SIGNAL SYSTEM | 823 8478 | SD | 300.000 | 300.000 | 0.000 | $75.00 | $0.00 | $0.00 | |
0086 | CONSTRUCTION TRAFFIC STRIPE(PAINT)(4" WIDE) | 857(A) 8839 | LF | 82,560.000 | 82,560.000 | 43,611.000 | 54,401.000 | $0.10 | $4,361.10 | $5,440.10 |
0087 | (PL)CONSTRUCTION ZONE PAVEMENT MARKERS(FLEX TAB)TYPE 2-2 | 857(E) 8890 | EA | 1,800.000 | 1,800.000 | 0.000 | $2.00 | $0.00 | $0.00 | |
0088 | PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 857(F) 8006 | LF | 7,400.000 | 7,400.000 | 995.000 | $0.30 | $0.00 | $298.50 | |
0089 | (SP)CONST.ZONE IMPACT ATTEN. | 871(B) 8705 | SD | 600.000 | 600.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0090 | (PL)TRUCK MOUNTED ATTENUATOR | 876(A) 8482 | SD | 600.000 | 600.000 | 0.000 | $5.00 | $0.00 | $0.00 | |
0091 | DELIVER PORTABLE LONGITUDINAL BARRIER | 877(B) 8484 | LF | 3,800.000 | 3,800.000 | 1,784.000 | 3,680.000 | $31.80 | $56,731.20 | $117,024.00 |
0092 | RELOCATION OF PORTABLE LONGITUDINAL BARRIER | 877(C) 8486 | LF | 3,800.000 | 3,800.000 | 0.000 | $1.00 | $0.00 | $0.00 | |
0093 | CONSTRUCTION SIGNS 0 TO 6.25 SF | 880(B) 8818 | SD | 9,000.000 | 9,000.000 | 232.000 | 3,677.000 | $0.80 | $185.60 | $2,941.60 |
0094 | CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 880(B) 8821 | SD | 10,200.000 | 10,200.000 | 349.000 | 3,235.000 | $1.50 | $523.50 | $4,852.50 |
0095 | CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 880(B) 8824 | SD | 13,500.000 | 13,500.000 | 376.000 | 4,464.000 | $1.00 | $376.00 | $4,464.00 |
0096 | CONSTRUCTION BARRICADES(TYPE III) | 880(C) 8842 | SD | 4,800.000 | 4,800.000 | 209.000 | 536.000 | $0.30 | $62.70 | $160.80 |
0097 | WING BARRICADES | 880(C) 8848 | SD | 1,200.000 | 1,200.000 | 60.000 | 732.000 | $1.00 | $60.00 | $732.00 |
0098 | VERTICAL PANELS | 880(D) 8854 | SD | 66,000.000 | 66,000.000 | 876.000 | 1,356.000 | $0.10 | $87.60 | $135.60 |
0099 | WARNING LIGHTS(TYPE A) | 880(E) 8860 | SD | 22,500.000 | 22,500.000 | 859.000 | 5,698.000 | $0.10 | $85.90 | $569.80 |
0100 | DRUMS | 880(F) 8878 | SD | 52,500.000 | 52,500.000 | 567.000 | 927.000 | $0.10 | $56.70 | $92.70 |
0101 | CHANNELIZER CONES | 880(G) 8890 | SD | 168,000.000 | 168,000.000 | 1,020.000 | 4,972.000 | $0.10 | $102.00 | $497.20 |
0102 | FLAGGER | 880(I) 8902 | SD | 600.000 | 600.000 | 0.000 | $0.00 | $0.00 | $0.00 | |
0103 | PORT.CHANGEABLE MESSAGE SIGN | 882(A) 8306 | SD | 628.000 | 628.000 | 6.000 | 94.000 | $5.00 | $30.00 | $470.00 |
Subtotals For Category 0300/TRAFFIC CONTROL | $62,662.30 | $137,678.80 | ||||||||
Fed/State Project Number: STP-126C(063) | Project: 20301(04) | Category: 0301/TRAFFIC SIGNING & STRIPING | ||||||||
0104 | RUMBLE STRIP-METHOD HMA-CON | 413(A) 4861 | LF | 41,280.000 | 41,280.000 | 0.000 | $0.10 | $0.00 | $0.00 | |
0105 | RUMBLE STRIP-CENTERLINE HMA-CON | 413(A) 4870 | LF | 20,640.000 | 20,640.000 | 0.000 | $0.20 | $0.00 | $0.00 | |
0106 | (PL)REMOVAL OF EXISTING SIGNS | 805(A) 8724 | EA | 20.000 | 20.000 | 0.000 | $25.00 | $0.00 | $0.00 | |
0107 | (PL)REMOVE & RESET EXISTING SIGNS | 805(D) 8756 | EA | 1.000 | 1.000 | 0.000 | $200.00 | $0.00 | $0.00 | |
0108 | SHEET ALUMINUM SIGNS | 850(A) 8110 | SF | 93.250 | 93.250 | 0.000 | $20.00 | $0.00 | $0.00 | |
0109 | 2" SQUARE TUBE POST | 851(C) 8324 | LF | 190.500 | 190.500 | 0.000 | $10.00 | $0.00 | $0.00 | |
0110 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 856(A) 8530 | LF | 82,560.000 | 82,560.000 | 0.000 | $0.40 | $0.00 | $0.00 | |
0111 | TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) | 856(A) 8555 | LF | 120.000 | 120.000 | 0.000 | $4.50 | $0.00 | $0.00 | |
8000 | (SP) TRAFFIC SURVEILLANCE, OHP (NON-BID) | 880(L)7310 | HOUR | 0.000 | 240.000 | 108.000 | $69.00 | $0.00 | $7,452.00 | |
Subtotals For Category 0301/TRAFFIC SIGNING & STRIPING | $0.00 | $7,452.00 | ||||||||
Fed/State Project Number: STP-126C(063) | Project: 20301(04) | Category: 0600/STAKING | ||||||||
0112 | CONSTRUCTION STAKING LEVEL II | 642(B) 0096 | LSUM | 1.000 | 1.000 | 0.500 | $150,000.00 | $0.00 | $75,000.00 | |
Subtotals For Category 0600/STAKING | $0.00 | $75,000.00 | ||||||||
Fed/State Project Number: STP-126C(063) | Project: 20301(04) | Category: 0640/CONSTRUCTION | ||||||||
0113 | SWPPP DOCUMENTATION AND MANAGEMENT | 220 2800 | LSUM | 1.000 | 1.000 | 0.250 | $15,000.00 | $0.00 | $3,750.00 | |
0114 | FIELD OFFICE | 640(A) 1426 | EA | 1.000 | 1.000 | 1.000 | $7,000.00 | $0.00 | $7,000.00 | |
0115 | MOBILIZATION | 641 1552 | LSUM | 1.000 | 1.000 | 0.860 | $616,500.00 | $0.00 | $530,190.00 | |
Subtotals For Category 0640/CONSTRUCTION | $0.00 | $540,940.00 | ||||||||
Subtotals For Project STP-126C(063) /20301(04) | $716,940.94 | $3,476,418.77 |