Oklahoma Department of Transportation
Final Estimate Affidavit

Contract ID: 090100   Estimate Number: 0005 , Final     Spec Year: 1999
Primary JP: 26133(04)   Residency: CLAREMORE (08300)     Contract No: 410863
Date Created: 01/04/2010   Contractor FEI: 731316732     Account No: 404800

Project Number(s): SSR-166N(228)SR, SSR-172N(447)SR
Contract Description: RESURFACE (ASPHALT) I-44: FROM I-244, EXTEND EAST. PROJECT LENGTH = 3.86 MILES
Primary County: ROGERS              
Name of Road: I-44              
Prime Contractor: BECCO CONTRACTORS, INC.           Time Charged: 57.00
    P.O. BOX 9159           Time Allowed: 73.00
    TULSA , OK   74157           Percent Time: 78.08 %

  Paid To Date: $889,361.36 Payable This Statement: $0.00

CONTRACTOR AFFIDAVIT
STATE OF ___________________ )  
  )     §  
COUNTY OF __________________ )  
The undersigned contractor or duly authorized agent, of lawful age, being first duly sworn, on oath say that this claim is true and correct.
Affiant further states that the work, services or materials as shown by this claim have been completed or supplied in accordance with the plans, specifications, orders, requests and all other terms of the contract. Affiant further states that (s)he is duly authorized agent of the contractor for the purpose of certifying the facts pertaining to the giving of things of value to government personnel in order to procure the contract or obtain payment; that (s)he is fully aware of the facts and circumstances surrounding the making of the contract and has been personally and directly involved in the proceedings leading to the procurement of the contract and the filing of this claim; and, neither the contractor nor anyone subject to the contractor's direction or control has been paid, given or donated or agreed to pay, give or donate to any officer or employee of the State of Oklahoma any money or other thing of value, either directly or
indirectly, in procuring the contract or obtaining payment. The affiant further certifies that all laborers, mechanics, apprentices and trainees employed by him/her or by any subcontractor performing work under the contract on the project have been paid wages at rates not less than those required by the contract provisions, and that the work performed by each such laborer, mechanic, apprentice or trainee conformed to the classifications set forth in the contract or training program provisions applicable to the wage rate paid.
Affiant hereby agrees that Contractor will accept this estimate as full compensation for all money due Contractor by the Department of Transportation, and hereby relinquish all claims, either in contract or in tort, which have arisen or which might arise out of the construction of said project. That to the best of my knowledge and belief, all indebtedness for labor, materials, fuel, equipment, equipment rental, parts, supplies, insurance premiums, and claims for items not specifically mentioned, which are attributable to performance of the work on this project or which were incorporated therein in any manner, have been paid in full, and that there are not now any presently outstanding, unpaid claims for such indebtedness; that my position with the company is such, that if there were any such outstanding claims of the nature specified herein, I would ordinarily be aware of them.
Further affiant sayeth not.                                
BECCO CONTRACTORS, INC.                               
 
_________________________________________________
Affiant Signature
 
_________________________________________________
Affiant Printed Name
                          PE Seal
_________________________________________________
Affiant Company Position
Subscribed and sworn to before me this ______ day of ____________, 20____
My Commission Number: ____________ My Commission Expires: ______________
   
_________________________________________________              
_________________________________________________
                    Professional Engineer Signature
              Oklahoma Department of Transportation
Corporate Seal
Notary Seal                  

Oklahoma Department of Transportation
Final Estimate Summary
Created:    01/04/2010
Contract ID: 090100   Estimate Number: 0005     Contract No: 410863
Residency: CLAREMORE (08300)   Estimate Type: Final     Account No: 404800

Project Number(s): SSR-166N(228)SR, SSR-172N(447)SR
Primary Job Piece No: 26133(04)
Contract Description: RESURFACE (ASPHALT) I-44: FROM I-244, EXTEND EAST. PROJECT LENGTH = 3.86 MILES
Primary County: ROGERS              
Name of Road: I-44              
Prime Contractor: BECCO CONTRACTORS, INC.              
    P.O. BOX 9159              
    TULSA , OK   74157              
Surety Company: MID-CONTINENT CASUALTY COMPANY              

Date Let: 01/22/2009 NTP Effective Date: 06/01/2009 Pay Period: 10/01/2009  TO  01/04/2010
Date Awarded: 02/02/2009 Date Work Began: 07/10/2009 Original Contract Time: 60
Date Contract Executed: 02/11/2009 Date Time Stopped: 08/31/2009 Current Time Charged: 57.00
Date NTP Issued: 02/12/2009 Completion Date: 08/31/2009 Current Time Allowed: 73.00
General Liability Expires: 03/01/2010 Workman's Comp Expires: 02/01/2010 Percent Time Used: 78.08 %
Specification Year: 1999        

Current Contract Amount: $925,485.09 Total to Date Prev to Date This Estimate
Bid Amount: $1,023,576.00 Participating: $0.00 $0.00 $0.00
Percent Complete: 96.10 % Non Participating: $925,485.10 $925,485.10 $0.00
Funds Available: $36,123.73 Total Earnings: $925,485.10 $925,485.10 $0.00
Unearned Balance: $134,214.64 Stockpiled Materials: $0.00 $0.00 $0.00
Gross Earnings: $925,485.10 $925,485.10 $0.00
Other Adjustments: $-36,123.74 $-36,123.74 $0.00
Liq Dam/Disincentive: $0.00 $0.00 $0.00
TOTAL: $889,361.36 $889,361.36 $0.00

Estimate Adjustment Detail

Contract ID: 090100   Estimate Number: 0005     Primary JP: 26133(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
001 Supplemental agreement changing work start date. Approved 06/24/2009 0.0 $0.00
002 Supplemental Agreement for Asphalt Deduct Approved 09/18/2009 0.0 $-32,749.86
003 Final Contract Item Quantities Approved 12/14/2009 0.0 $-65,341.05


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
No material stockpiles have been created for this contract.
Subtotals For Stockpile Payments $0.00


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
No liquidated damages have been assessed on this contract.


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
26133(04) 0001 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0001 0.00 $0.00 $-8,238.44
26133(04) 0001 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0002 0.00 $0.00 $-15,850.17
26133(04) 0001 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) * Material Discrepancy Adjustments 0003 -22.68 $78.00 $-1,769.04
26133(04) 0001 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0003 0.00 $0.00 $-5,363.47
26133(04) 0001 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) * Material Discrepancy Adjustments 0004 22.68 $78.00 $1,769.04
26133(04) 0001 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0004 0.00 $0.00 $0.03
26133(05) 0008 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0001 0.00 $0.00 $-1,735.74
26133(05) 0008 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0002 0.00 $0.00 $-3,733.33
26133(05) 0008 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) Asphalt Binder Adjustment 0003 0.00 $0.00 $-1,202.62
26133(05) 0008 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) * Material Discrepancy Adjustments 0003 -419.87 $78.00 $-32,749.86
26133(05) 0008 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) * Material Discrepancy Adjustments 0004 419.87 $78.00 $32,749.86
Subtotals For Line Item Adjustments $-36,123.74
* = User applied Line Item Adjustments


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 090100   Estimate Number: 0005     Primary JP: 26133(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    SSR-166N(228)SR Project:    26133(04) Category:    0400/ROADWAY SSR-166N(228)SR
0001 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) 411(S4) 5950 TON 8,070.000 7,654.980   7,654.980 $78.00 $0.00 $597,088.44
0002 COLD MILLING PAVEMENT 417 5267 SY 71,700.000 70,436.140   70,436.140 $1.50 $0.00 $105,654.22
0003 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 67,560.000 57,437.000   57,437.000 $0.40 $0.00 $22,974.80
0004 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   1.000 $35,000.00 $0.00 $35,000.00
0005 TRAFFIC SURVEILLANCE, POLICE 880(L) 8911 HOUR 300.000 34.500   34.500 $60.00 $0.00 $2,070.00
0006 PORT.CHANGEABLE MESSAGE SIGN 882(B) 8306 SD 50.000 46.000   46.000 $50.00 $0.00 $2,300.00
0007 (PL)REMOVAL OF CLASS C PAVEMENT MARKERS 890(A) 8702 EA 280.000 272.000   272.000 $11.00 $0.00 $2,992.00
8000 DEDUCTION FOR FAILING MATERIAL 105 2100 LSUM 0.000 -1.000 0.000 -1.000 $32,749.86 $0.00 $-32,749.86
Subtotals For Category     0400/ROADWAY SSR-166N(228)SR    $0.00 $735,329.60
Subtotals For Project SSR-166N(228)SR /26133(04) $0.00 $735,329.60


Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    SSR-172N(447)SR Project:    26133(05) Category:    0400/ROADWAY SSR-172N(447)SR
0008 (SP)ASPHALT CONCRETE TYPE S4(PG 76-28 OK) 411(S4) 5950 TON 1,650.000 1,732.840   1,732.840 $78.00 $0.00 $135,161.52
0009 COLD MILLING PAVEMENT 417 5267 SY 14,650.000 15,301.390   15,301.390 $2.00 $0.00 $30,602.78
0010 TRAFFIC STRIPE(PLASTIC)(4" WIDE) 855(A) 8812 LF 15,980.000 11,938.000   11,938.000 $0.40 $0.00 $4,775.20
0011 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   1.000 $15,000.00 $0.00 $15,000.00
0012 TRAFFIC SURVEILLANCE, POLICE 880(L) 8911 HOUR 300.000 35.000   35.000 $60.00 $0.00 $2,100.00
0013 PORT.CHANGEABLE MESSAGE SIGN 882(B) 8306 SD 45.000 38.000   38.000 $50.00 $0.00 $1,900.00
0014 (PL)REMOVAL OF CLASS C PAVEMENT MARKERS 890(A) 8702 EA 120.000 56.000   56.000 $11.00 $0.00 $616.00
Subtotals For Category     0400/ROADWAY SSR-172N(447)SR    $0.00 $190,155.50
Subtotals For Project SSR-172N(447)SR /26133(05) $0.00 $190,155.50