Oklahoma Department of Transportation
Progressive Estimate Summary
Created:    01/03/2008
Contract ID: 060249   Estimate Number: 0008     Contract No: 211063
Residency: TULSA (08100)   Estimate Type: Progressive     Account No: 400800

Project Number(s): HSIPG-172N(304)TR
Primary Job Piece No: 22959(04)
Contract Description: DELINEATION AND SIGNING PROJECT TULSA METRO-AREA: AT VARIOUS LOCATIONS. PROJECT LENGTH = 0.00 MILE
Primary County: TULSA              
Name of Road: I-44              
Prime Contractor: ACTION SAFETY SUPPLY CO.              
    P.O. BOX 270238              
    OKLAHOMA CITY , OK   73137-0238              
Surety Company: EMPLOYERS MUTUAL CASUALTY COMPANY              

Date Let: 03/15/2007 NTP Effective Date: 07/15/2007 Pay Period: 12/01/2007  TO  12/31/2007
Date Awarded: 04/02/2007 Date Work Began: 07/30/2007 Original Contract Time: 120
Date Contract Executed: 04/12/2007 Date Time Stopped: Current Time Charged: 170.00
Date NTP Issued: 04/17/2007 Completion Date: Current Time Allowed: 150.00
General Liability Expires: 05/01/2008 Workman's Comp Expires: 07/01/2008 Percent Time Used: 113.33 %
Specification Year: 1999     Date Approved:

Current Contract Amount: $408,666.43 Total to Date Prev to Date This Estimate
Bid Amount: $408,666.43 Participating: $347,743.79 $255,954.60 $91,789.19
Percent Complete: 75.37 % Non Participating: $0.00 $0.00 $0.00
Funds Available: $100,642.13 Total Earnings: $347,743.79 $255,954.60 $91,789.19
Unearned Balance: $100,642.13 Stockpiled Materials: $10,889.51 $30,143.37 $-19,253.86
Gross Earnings: $358,633.30 $286,097.97 $72,535.33
Other Adjustments: $-40,609.00 $-8,170.00 $-32,439.00
Liq Dam/Disincentive: $-10,000.00 $-3,500.00 $-6,500.00
TOTAL: $308,024.30 $274,427.97 $33,596.33

Estimate Adjustment Detail

Contract ID: 060249   Estimate Number: 0008     Primary JP: 22959(04)



CHANGE ORDER HISTORY
Change Order Nbr. Change Order Description Status Approval Date Contract Time Adjustment Total Change Order Amount
No change orders have been created for this contract.


STOCKPILE PAYMENT HISTORY
Project Line Nbr Stockpile Description Adjustment Type Estimate Nbr Adjusted Amount
22959(04) 0004 Sign blanks, sheeting Stockpiled Material Initial Payment 0001 $61,716.65
22959(04) 0004 Sign blanks, sheeting Stockpiled Material Adjustment 0002 $-8,409.27
22959(04) 0004 Sign blanks, sheeting Stockpiled Material Adjustment 0006 $-1,836.58
22959(04) 0004 Sign blanks, sheeting Stockpiled Material Adjustment 0007 $-23,458.49
22959(04) 0004 Sign blanks, sheeting Stockpiled Material Adjustment 0008 $-19,253.86
22959(04) 0005 12" Extruded Aluminum, sheeting, hardware Stockpiled Material Initial Payment 0001 $28,231.58
22959(04) 0005 12" Extruded Aluminum, sheeting, hardware Stockpiled Material Adjustment 0006 $-25,234.95
22959(04) 0005 12" Extruded Aluminum, sheeting, hardware Stockpiled Material Adjustment 0007 $-2,996.63
22959(04) 0008 Square tube post Stockpiled Material Initial Payment 0001 $10,605.14
22959(04) 0008 Square tube post Stockpiled Material Adjustment 0002 $-3,421.03
22959(04) 0008 Square tube post Stockpiled Material Adjustment 0006 $-2,258.33
22959(04) 0008 Square tube post Stockpiled Material Adjustment 0007 $-4,925.78
22959(04) 0012 IRS: Dellineator, Sheeting, Base Stockpiled Material Initial Payment 0005 $32,334.10
22959(04) 0012 IRS: Dellineator, Sheeting, Base Stockpiled Material Adjustment 0006 $-28,295.48
22959(04) 0012 IRS: Dellineator, Sheeting, Base Stockpiled Material Adjustment 0007 $-1,907.56
Subtotals For Stockpile Payments $10,889.51


LIQUIDATED DAMAGES HISTORY
Adjustment Description Estimate Nbr Time Units Rate Adjustment Amount
System Application of Liquidated Damages 0007 -7.0 $500.00 $-3,500.00
System Application of Liquidated Damages 0008 -13.0 $500.00 $-6,500.00


CONTRACT ADJUSTMENTS HISTORY
Adjustment Description Estimate Nbr Adjustment Amount
No general contract adjustments have been created on this contract.
Subtotals For Contract Adjustments $0.00


LINE ITEM ADJUSTMENT HISTORY
Project Item Nbr Line Item Description Adjustment Type Estimate Nbr Adj Quantity Unit Price Adjusted Amount
22959(04) 0003 STRUCTURAL CONCRETE Material Discrepancy Adjustments 0002 -12.32 $88.00 $-1,084.16
22959(04) 0003 STRUCTURAL CONCRETE Material Discrepancy Adjustments 0006 12.32 $88.00 $1,084.16
22959(04) 0006 3"@7.58 GALV.STEEL PIPE POST Material Discrepancy Adjustments 0008 -2,684.25 $12.00 $-32,211.00
22959(04) 0007 1 3/4" SQUARE TUBE POST Material Discrepancy Adjustments 0006 -228.00 $4.00 $-912.00
22959(04) 0007 1 3/4" SQUARE TUBE POST Material Discrepancy Adjustments 0007 -294.00 $4.00 $-1,176.00
22959(04) 0007 1 3/4" SQUARE TUBE POST Material Discrepancy Adjustments 0008 -30.00 $4.00 $-120.00
22959(04) 0008 2 1/4" SQUARE TUBE POST Material Discrepancy Adjustments 0007 -1,202.50 $4.00 $-4,810.00
22959(04) 0009 BARRIER DELINEATORS(TYPE 1, CODE 1) Material Discrepancy Adjustments 0008 -18.00 $6.00 $-108.00
22959(04) 0010 BARRIER DELINEATORS(TYPE 2, CODE 1) Material Discrepancy Adjustments 0002 -786.00 $6.00 $-4,716.00
22959(04) 0010 BARRIER DELINEATORS(TYPE 2, CODE 1) Material Discrepancy Adjustments 0003 786.00 $6.00 $4,716.00
22959(04) 0010 BARRIER DELINEATORS(TYPE 2, CODE 1) Material Discrepancy Adjustments 0006 -212.00 $6.00 $-1,272.00
Subtotals For Line Item Adjustments $-40,609.00


MILESTONE ADJUSTMENTS
Milestone Number Milestone Description Time Allowed Time Used Rate Total
No milestones exist for this contract.

Line Item Detail

Contract ID: 060249   Estimate Number: 0008     Primary JP: 22959(04)



Line Item Number Item Description Item Number Units Bid Qty Current Quantity Quantity Paid This Est. Quantity Paid To Date Unit Price Amount Paid This Est. Amount Paid To Date
Fed/State Project Number:    HSIPG-172N(304)TR Project:    22959(04) Category:    0300/TRAFFIC
0001 CLASS A CONCRETE 509(B) 0321 CY 65.550 65.550 30.820 64.400 $900.00 $27,738.00 $57,960.00
0002 REINFORCING STEEL 511(A) 0332 LB 9,120.000 9,120.000 4,544.000 8,960.000 $1.00 $4,544.00 $8,960.00
0003 STRUCTURAL CONCRETE 804(A) 2915 CY 82.250 82.250 0.630 35.560 $88.00 $55.44 $3,129.28
0004 SHEET ALUMINUM SIGNS 850(A) 8110 SF 7,644.950 7,644.950 2,146.500 5,904.000 $11.50 $24,684.75 $67,896.01
0005 EXTRUDED ALUMINUM PANEL SIGNS 850(B) 8112 SF 3,311.500 3,311.500 20.000 3,011.500 $13.00 $260.00 $39,149.50
0006 3"@7.58 GALV.STEEL PIPE POST 851(B) 3218 LF 3,990.000 3,990.000 2,684.250 2,684.250 $12.00 $32,211.00 $32,211.00
0007 1 3/4" SQUARE TUBE POST 851(C) 8321 LF 1,210.000 1,210.000 30.000 552.000 $4.00 $120.00 $2,208.00
0008 2 1/4" SQUARE TUBE POST 851(C) 8327 LF 7,378.000 7,378.000 -443.000 6,608.500 $4.00 $-1,772.00 $26,434.00
0009 BARRIER DELINEATORS(TYPE 1, CODE 1) 853 9060 EA 1,740.000 1,740.000 414.000 2,897.000 $6.00 $2,484.00 $17,382.00
0010 BARRIER DELINEATORS(TYPE 2, CODE 1) 853 9063 EA 5,220.000 5,220.000 244.000 3,694.000 $6.00 $1,464.00 $22,164.00
0011 GUARDRAIL DELINEATORS(TYPE 1, CODE 1) 853 9066 EA 500.000 500.000   0.000 $3.25 $0.00 $0.00
0012 IMPACT RECOVERY SYSTEM (I.R.S.) 880(B) 8828 EA 339.000 339.000   285.000 $120.00 $0.00 $34,200.00
0013 TUBE CHANNELIZERS 880(G) 8887 EA 10.000 10.000   10.000 $45.00 $0.00 $450.00
0014 CONSTRUCTION TRAFFIC CONTROL 880(J) 8905 LSUM 1.000 1.000   1.000 $6,800.00 $0.00 $6,800.00
0015 (PL)REMOVAL OF EXISTING SIGNS 890(A) 8722 LSUM 1.000 1.000   1.000 $6,800.00 $0.00 $6,800.00
Fed/State Project Number:    HSIPG-172N(304)TR Project:    22959(04) Category:    0600/MOBILIZATION
0016 MOBILIZATION 641 1552 LSUM 1.000 1.000   1.000 $22,000.00 $0.00 $22,000.00
Subtotals For Project HSIPG-172N(304)TR /22959(04) $91,789.19 $347,743.79